Permit: T14CM03978
Permit Details
Apply Date:
06/26/2014
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
BUSINESS REMODEL & EXPANSION
Architects:
- BARCUS, BARRY RAY
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T14CM03978
Permit Status: C of o
Permit Description: BUSINESS REMODEL & EXPANSION
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/20/2015 | REVISION - - 1ST | 01/20/2015 | COMPLETED |
| 01/20/2015 | REVISION - - 1ST | 02/06/2015 | COMPLETED |
| 06/26/2014 | PLANS OK TO SUBMIT - COMM | 07/01/2014 | COMPLETED |
| 07/01/2014 | COMMERCIAL - TI | 08/18/2014 | COMPLETED |
| 08/18/2014 | RESUBMITTAL - TI ALL | 09/10/2014 | COMPLETED |
| 09/10/2014 | RESUBMITTAL | 11/19/2014 | COMPLETED |
| 11/19/2014 | RESUBMITTAL | 11/19/2014 | COMPLETED |
| 11/19/2014 | RESUBMITTAL | 01/20/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM03978
Permit Status: C of o
Permit Description: BUSINESS REMODEL & EXPANSION
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/26/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM03978
Permit Description: BUSINESS REMODEL & EXPANSION
Total Completed Inspections - 45
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/19/2014 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | REMODEL AREAS; EXCEPT FOR RESTROOMS - OK TO SHEETROCK PROGRESS AREAS |
| 12/19/2014 | FRAMING | JBURGE | Approved | REMODEL AREA GL: D-X; 1-6 - EXCEPT FOR RESTROOMS |
| 12/19/2014 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 12/19/2014 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 12/22/2014 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | SITE WALL FOOTING - OK TO POUR |
| 12/22/2014 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
| 12/31/2014 | ELECTRIC - PROGRESS | JBURGE | Approved | 3" POWER CONDUIT - RIDE NOW MAIN ENTRY (EAST) TO NORTH MAIN POWER CABINET: 3" CONDUIT LINE FOR REPAIR AREA; 6 @ 1" CONDUITS FOR PARKING LOT LIGHTS |
| 12/31/2014 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | 2" WATERLINE FROM EAST ENTRY TO RIDE NOW - NORTH TO MAIN HOOK-UP - OK TO COVER |
| 12/31/2014 | ELECTRIC - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 12/31/2014 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | IVRS - Inspection :* |
| 03/11/2015 | PLUMBING - INTERMEDIATE | JBURGE | Approved | PLUMBING IN WALLS |
| 03/11/2015 | PLUMBING - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 03/24/2015 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | AWAITING SW GAS HOOK-UP LINE |
| 03/24/2015 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | IVRS - Inspection :* |
| 03/24/2015 | PLUMBING - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 04/14/2015 | BUILDING ABOVE CEILING | JBURGE | Approved | OK TO SET CEILING TILES |
| 04/14/2015 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 04/14/2015 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
| 05/08/2015 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | OK TO SET CEILING TILES |
| 05/08/2015 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 05/08/2015 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/23/2015 | ELECTRIC - UNDERGROUND | jburge | Approved | |
| 06/23/2015 | MECHANICAL - INTERMEDIATE | jburge | Approved | |
| 06/23/2015 | PLUMBING - PROGRESS | jburge | Approved | |
| 06/23/2015 | PLUMBING - ROOF DRAINS | JBURGE | Approved | IVRS - Inspection :* |
| 06/23/2015 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
| 06/23/2015 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/23/2015 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 06/23/2015 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
| 06/23/2015 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 06/23/2015 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 06/23/2015 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 06/23/2015 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 06/24/2015 | GAS CLEARANCE | JBURGE | Approved | |
| 06/30/2015 | STEM WALL/RETAINING WALL | jburge | Approved | PER JBURGE |
| 06/30/2015 | STUCCO MESH | jburge | Approved | PER JBURGE |
| 06/30/2015 | BUILDING - PROGRESS | jburge | Approved | PER JBURGE |
| 06/30/2015 | FIRE - FINAL | Nsprenger | Approved | All emergency lighting operating. All exit signs in place. Fire extinguishers withing 75 of all places. |
| 06/30/2015 | FIRE SPKLR - FINAL | Nsprenger | Approved | All fans shut down upon water flow alarm. |
| 06/30/2015 | NPPO - FINAL | MRUSSO | Approved | |
| 06/30/2015 | SIGN - FINAL | MRUSSO | Approved | |
| 07/06/2015 | RIGHT OF WAY - FINAL | JC | Approved | |
| 07/20/2015 | BUILDING - FINAL | JBURGE | Approved | |
| 07/21/2015 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 07/21/2015 | ENGINEERING - FINAL | MRUSSO | Approved |