Permit: T14CM03879
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
8182 S CAMINO DE CAFE
Address NEW:
8182 S CAMINO DE CAFE
Apply Date:
06/23/2014
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
NEW WAREHOUSE W/OFFICE AREA
Architects:
- PAUL BISHOP
Contractors:
- SIERRA LAND SURVEYING AND DEVELO
Permit Reviews
Permit Number - T14CM03879
Permit Status: C of o
Permit Description: NEW WAREHOUSE W/OFFICE AREA
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/23/2014 | PLANS OK TO SUBMIT - COMM | 06/24/2014 | COMPLETED |
| 06/24/2014 | COMMERCIAL - NEW | 07/14/2014 | COMPLETED |
| 07/14/2014 | RESUBMITTAL - TI ALL | 07/23/2014 | COMPLETED |
| 07/23/2014 | RESUBMITTAL - TI ALL | 07/25/2014 | COMPLETED |
| 07/25/2014 | RESUBMITTAL | 08/06/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T14CM03879
Permit Status: C of o
Permit Description: NEW WAREHOUSE W/OFFICE AREA
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/23/2014 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM03879
Permit Description: NEW WAREHOUSE W/OFFICE AREA
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/15/2014 | PLUMBING - ROUGH, SOIL | WLAHR | Approved | IVRS - Inspection :* |
| 08/26/2014 | ELECTRIC - UFER | WLAHR | Approved | #4 COPPER TIED REBAR NORTHEAST CORNER OF WAREHOUSE |
| 08/26/2014 | BUILDING PRE-SLAB | WLAHR | Approved | IVRS - Inspection :* |
| 09/29/2014 | FRAMING | WLAHR | Approved | IVRS - Inspection :* |
| 09/29/2014 | EXT METAL CLIPS/EXT SHEATHING | WLAHR | Approved | IVRS - Inspection :* |
| 10/09/2014 | PLUMBING - SEWER HCS CONNECT | JBURGE | Approved | IVRS - Inspection :* |
| 10/09/2014 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | IVRS - Inspection :* |
| 10/09/2014 | ELECTRIC - UNDERGROUND | JBURGE | Approved | IVRS - Inspection :* |
| 10/09/2014 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
| 10/09/2014 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
| 10/13/2014 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 10/13/2014 | PLUMBING - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 10/13/2014 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 10/13/2014 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 10/24/2014 | SHEET ROCK NAILING | WLAHR | Approved | IVRS - Inspection :* |
| 11/19/2014 | STEM WALL/RETAINING WALL | RMORENO | Approved | IVRS - Inspection :* |
| 11/19/2014 | EXCAVATION/LAYOUT REBAR & ZON | RMORENO | Approved | IVRS - Inspection :* |
| 11/26/2014 | ELECTRIC - TEMPORARY SERVICE | RMORENO | Approved | IVRS - Inspection :* |
| 11/28/2014 | TEP CLEARANCE - AM | RMORENO | Approved | TEC |
| 12/10/2014 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 12/10/2014 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 12/10/2014 | PLUMBING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 12/10/2014 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 12/10/2014 | ELECTRIC - OUTDOOR LIGHTING | JBURGE | Approved | IVRS - Inspection :* |
| 12/10/2014 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 12/10/2014 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 12/10/2014 | RIGHT OF WAY - FINAL | JC/fbs | Approved | |
| 12/11/2014 | NPPO - FINAL | MRUSSO | Approved | |
| 12/11/2014 | SIGN - FINAL | MRUSSO | Approved | |
| 12/15/2014 | FIRE - FINAL | CSCHULTZ | Approved | |
| 12/15/2014 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 12/19/2014 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 12/19/2014 | ENGINEERING - FINAL | MRUSSO | Approved |