Permit: T14CM00045
Permit Details
Apply Date:
01/03/2014
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
RETAIL STORE
Architects:
- BLAIR LEACH
Contractors:
- E J C CONSTRUCTION
Permit Reviews
Permit Number - T14CM00045
Permit Status: C of o
Permit Description: RETAIL STORE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/03/2014 | PLANS OK TO SUBMIT - COMM | 01/03/2014 | COMPLETED |
01/06/2014 | COMMERCIAL - TI | 02/12/2014 | COMPLETED |
02/12/2014 | RESUBMITTAL | 03/06/2014 | COMPLETED |
03/06/2014 | RESUBMITTAL | 03/07/2014 | COMPLETED |
03/07/2014 | RESUBMITTAL | 03/10/2014 | ACTIVE |
03/07/2014 | WALK THRU - COMM | 03/07/2014 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T14CM00045
Permit Description: RETAIL STORE
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/23/2014 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | OK TO COVER PROGRESS AREAS |
05/23/2014 | PLUMBING - ROUGH, SOIL | JBURGE | Approved | IVRS - Inspection :* |
07/16/2014 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | OK TO SHEET ROCK PROGRESS AREA |
07/16/2014 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
07/16/2014 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
08/13/2014 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
09/04/2014 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
09/04/2014 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
09/04/2014 | PLUMBING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
09/04/2014 | PLUMBING - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
09/04/2014 | PLUMBING - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
09/04/2014 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
09/04/2014 | PLUMBING - PRE SLAB | JBURGE | Approved | IVRS - Inspection :* |
09/04/2014 | ELECTRIC - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
09/04/2014 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
09/11/2014 | FIRE - ALARM FINAL | CSCHULTZ | Approved | Corrections made and passed |
09/11/2014 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | Corrections made |
09/17/2014 | BUILDING - PROGRESS | JBURGE | Approved | |
09/17/2014 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
09/17/2014 | PLUMBING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
09/17/2014 | ELECTRIC - FINAL | JBURGE | Approved | IVRS - Inspection :* |
09/17/2014 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
09/17/2014 | FIRE - FINAL | CBASALDUA | Approved |