Permit: T13CM05792
Permit Details
Apply Date:
09/19/2013
Applicant:
RICHARD FE TOM
Description:
NEW APARTMENT COMMUNITY BUILDING
Architects:
- TOM, RICHARD FE
Contractors:
- SHEA CONNELLY DEVELOPMENT LLC
Permit Reviews
Permit Number - T13CM05792
Permit Status: C of o
Permit Description: NEW APARTMENT COMMUNITY BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/05/2014 | WALK THRU - COMM | 06/05/2014 | COMPLETED |
| 06/05/2014 | REVISION - - 1ST | 06/11/2014 | COMPLETED |
| 09/19/2013 | PLANS OK TO SUBMIT - COMM | 09/20/2013 | COMPLETED |
| 09/23/2013 | COMMERCIAL - NEW | 10/24/2013 | COMPLETED |
| 10/24/2013 | RESUBMITTAL | 11/19/2013 | COMPLETED |
| 11/24/2014 | REVISION - - 1ST | 11/24/2014 | COMPLETED |
| 12/20/2013 | RESUBMITTAL | 01/10/2014 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM05792
Permit Status: C of o
Permit Description: NEW APARTMENT COMMUNITY BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/19/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM05792
Permit Description: NEW APARTMENT COMMUNITY BUILDING
Total Completed Inspections - 40
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/20/2014 | SITE - SEWER | RLEDONNE | Approved | |
| 02/20/2014 | PLUMBING - PRE SLAB | RLEDONNE | Approved | |
| 02/20/2014 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | |
| 03/07/2014 | ROOF NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 03/07/2014 | EXT METAL CLIPS/EXT SHEATHING | MRAMBER | Approved | IVRS - Inspection :* |
| 03/14/2014 | PLUMBING - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/19/2014 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | INSTALLATION PRACTICES OK PER L. HANLEY |
| 06/19/2014 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | E.F. IN JANITOR CLOSET |
| 06/19/2014 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/19/2014 | PLUMBING - YARD WTR LINE/TEST | MRAMBER | Approved | IVRS - Inspection :* |
| 06/19/2014 | ELECTRIC - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 06/26/2014 | U VALUE FOR WINDOW | MRAMBER | Approved | IVRS - Inspection :* |
| 08/12/2014 | FIRE SPKLR - OH PIPING & HYDRO | CSCHULTZ | Approved | 200 PSI for 2 hours APPROVED-CRS- Told contractor about installation starting to touch the tops of the upright sprinklers will need to re-wire keeping insulation off of heads.-CRS- |
| 08/18/2014 | PLUMBING - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 08/18/2014 | ELECTRIC - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 08/18/2014 | ELECTRIC - UNDERGROUND | MRAMBER | Approved | IVRS - Inspection :* |
| 08/18/2014 | ELECTRIC - UFER | MRAMBER | Approved | IVRS - Inspection :* |
| 08/18/2014 | BUILDING ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 08/18/2014 | BUILDING PRE-SLAB | MRAMBER | Approved | IVRS - Inspection :* |
| 08/21/2014 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | TRASH CORRAL OK TO GROUT |
| 08/21/2014 | EXCAVATION/LAYOUT REBAR & ZON | MRAMBER | Approved | IVRS - Inspection :* |
| 08/28/2014 | FIREWALL/FIREBARRIER/FIRESTOP | MRAMBER | Approved | IVRS - Inspection :* |
| 08/28/2014 | FRAMING | MRAMBER | Approved | IVRS - Inspection :* |
| 09/04/2014 | SHEET ROCK NAILING | MRAMBER | Approved | IVRS - Inspection :* |
| 09/04/2014 | STUCCO MESH | MRAMBER | Approved | IVRS - Inspection :* |
| 11/26/2014 | BUILDING - PROGRESS | MRAMBER | Approved | RE BAR AT TRASH CORRAL OK |
| 11/26/2014 | BUILDING - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
| 01/23/2015 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | ALL SITE WALLS ON PROPERTY LINE UNDER 7' IN HEIGHT |
| 01/23/2015 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | IVRS - Inspection :* |
| 07/09/2015 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 07/09/2015 | ELECTRIC - OUTDOOR LIGHTING | JMILITEL | Approved | IVRS - Inspection :* |
| 07/14/2015 | TEP CLEARANCE - AM | AQUIROZ | Approved | ECO |
| 10/01/2015 | PLUMBING - PROGRESS | MPUGH | Approved | |
| 10/01/2015 | MECHANICAL - FINAL | MPUGH1 | Approved | IVRS - Inspection :* |
| 10/01/2015 | PLUMBING - FINAL | MPUGH1 | Approved | IVRS - Inspection :* |
| 10/01/2015 | OUTDOOR LIGHTING FINAL | MPUGH1 | Approved | IVRS - Inspection :* |
| 10/01/2015 | ELECTRIC - FINAL | MPUGH1 | Approved | IVRS - Inspection :* |
| 10/05/2015 | BUILDING - FINAL | MPUGH1 | Approved | IVRS - Inspection :* |
| 11/18/2015 | FIRE SPKLR - FINAL | CBASALDUA | Approved | |
| 11/18/2015 | FIRE - FINAL | CBASALDUA | Approved |