Permit: T13CM03780
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
1549 W SAINT MARYS RD
Address NEW:
1549 W SAINT MARYS RD
Apply Date:
06/21/2013
Applicant:
N/A
Description:
RETAIL
Contractors:
- H C I CONSTRUCTION INCORPORATED
Permit Reviews
Permit Number - T13CM03780
Permit Status: C of o
Permit Description: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/21/2013 | PLANS OK TO SUBMIT - COMM | 06/21/2013 | COMPLETED |
| 06/21/2013 | COMMERCIAL - TI | 07/05/2013 | COMPLETED |
| 07/19/2013 | RESUBMITTAL | 07/24/2013 | COMPLETED |
| 07/24/2013 | RESUBMITTAL | 08/28/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T13CM03780
Permit Status: C of o
Permit Description: RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/21/2013 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T13CM03780
Permit Description: RETAIL
Total Completed Inspections - 29
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/30/2013 | PLUMBING - PRE SLAB | RMYERS | Approved | |
| 08/30/2013 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | |
| 08/30/2013 | ELECTRIC - INTERMEDIATE | RMYERS | Approved | |
| 08/30/2013 | ELECTRIC - UNDERGROUND | RMYERS | Approved | |
| 08/30/2013 | FRAMING | RMYERS | Approved | |
| 09/20/2013 | RIGHT OF WAY - FINAL | TW | Approved | |
| 09/23/2013 | NPPO - FINAL | MRUSSO | Approved | |
| 09/23/2013 | SIGN - FINAL | MRUSSO | Approved | |
| 09/23/2013 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 09/23/2013 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 09/27/2013 | FIRE - ALARM FINAL | wmotto | Approved | |
| 09/27/2013 | FIRE SPKLR - FINAL | wmotto | Approved | |
| 09/27/2013 | FIRE - FINAL | wmotto | Approved | |
| 09/27/2013 | MECHANICAL - ABOVE CEILING | RMYERS | Approved | |
| 09/27/2013 | MECHANICAL - INTERMEDIATE | RMYERS | Approved | |
| 09/27/2013 | PLUMBING - PROGRESS | RMYERS | Approved | |
| 09/27/2013 | PLUMBING - ABOVE CEILING | RMYERS | Approved | |
| 09/27/2013 | PLUMBING - INTERMEDIATE | RMYERS | Approved | |
| 09/27/2013 | SHEET ROCK NAILING | RMYERS | Approved | |
| 09/27/2013 | BUILDING ABOVE CEILING | RMYERS | Approved | |
| 09/27/2013 | ELECTRIC - ABOVE CEILING | RMYERS | Approved | |
| 09/30/2013 | MECHANICAL - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 09/30/2013 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 09/30/2013 | ELECTRIC - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 09/30/2013 | BUILDING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 09/30/2013 | MECHANICAL - FINAL | RMYERS | Approved | 1. Require a real air balance report. Contractor to verify all required work before calling final- work not performed will require a letter from the archetect or engineer of record. |
| 09/30/2013 | PLUMBING - FINAL | RMYERS | Approved | 1. Insulation, TMV, check all work |
| 09/30/2013 | BUILDING - FINAL | RMYERS | Approved | Require all other inspections. |
| 09/30/2013 | ELECTRIC - FINAL | RMYERS | Approved | 1. Finish panel and labeling. |