Permit Details

Status:
C of o
Type:
COMMERCIAL ADDITION
Apply Date:
03/18/2013
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
ADDITION: MEDICAL OFFICE
Contractors:
  • CALDWELL CONSTRUCTION L L C *C*

Permit Reviews

Permit Number - T13CM01537
Permit Status: C of o
Permit Description: ADDITION: MEDICAL OFFICE
Start Date Submittal Complete Date Status  
02/25/2014 REVISION - - 2ND 02/25/2014 COMPLETED Review Details
03/18/2013 PLANS OK TO SUBMIT - COMM 03/27/2013 COMPLETED Review Details
03/28/2013 COMMERCIAL - TI 06/10/2013 COMPLETED Review Details
06/10/2013 RESUBMITTAL 06/24/2013 COMPLETED Review Details
12/30/2013 REVISION - - 1ST 12/30/2013 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T13CM01537
Permit Status: C of o
Permit Description: ADDITION: MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
Date Name
03/18/2013 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T13CM01537
Permit Description: ADDITION: MEDICAL OFFICE
Total Completed Inspections - 40
Date Description Inspector Results Comments
10/11/2013 BUILDING PRE-SLAB BSTEVENS Approved IVRS - Inspection :*
10/23/2013 REINFORCED MASONRY PRE-GROUT BBENEDON Approved IVRS - Inspection :*
12/18/2013 PLUMBING - PRE SLAB BBENEDON Approved IVRS - Inspection :*
12/18/2013 PLUMBING - ROUGH, SOIL BBENEDON Approved IVRS - Inspection :*
12/18/2013 SHEET ROCK NAILING BBENEDON Approved IVRS - Inspection :*
12/18/2013 U VALUE FOR WINDOW BBENEDON Approved IVRS - Inspection :*
12/18/2013 FRAMING BBENEDON Approved IVRS - Inspection :*
12/20/2013 ELECTRIC - ABOVE CEILING BBENEDON Approved NO LIGHTS INSTALLED. PROVIDE ACCESS TO DISCONNECTS. CONDUITS OK
12/20/2013 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
12/20/2013 ELECTRIC - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
12/20/2013 ELECTRIC - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
12/23/2013 MECHANICAL - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
12/24/2013 MECHANICAL - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
12/24/2013 STEM WALL/RETAINING WALL BBENEDON Approved IVRS - Inspection :*
12/24/2013 EXCAVATION/LAYOUT REBAR & ZON BBENEDON Approved IVRS - Inspection :*
12/26/2013 BUILDING ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
12/26/2013 FIREWALL/FIREBARRIER/FIRESTOP BBENEDON Approved IVRS - Inspection :*
12/26/2013 PLUMBING - PROGRESS BBENEDON Approved IVRS - Inspection :*
12/27/2013 FIRE SPKLR - FINAL CSCHULTZ Approved Not ready asking for Temp C of O told them they need building offical approval on that.
12/27/2013 TEP CLEARANCE - AM bbenedon Approved INCR
12/30/2013 BUILDING - FINAL LHANLY Approved OK TCO PER DISCUSSION WITH BRIAN. MINOR ITEMS AND PERMIT CLEAN-UP REMAIN
12/30/2013 FIRE - FINAL CSCHULTZ Approved Temp C of O okay no public use
12/30/2013 FIRE - FINAL TFD Approved ok tco per carl tfd
12/31/2013 BUILDING - PROGRESS BBENEDON Approved STUCCO MESH OK. EXISTING IRR BACKFLOW REQ TEST DUE TO NEW UPSTREAM CONNECTION. CONDENSATE FOR FC 9 NOT PER PLAN.
12/31/2013 ELECTRIC - SERVICE UPGRADE BBENEDON Approved CLEARANCE PROVIDED - REV REQUIRED
12/31/2013 BUILDING - PROGRESS BBENEDON Approved IVRS - Inspection :*
12/31/2013 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
12/31/2013 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
12/31/2013 PLUMBING - GAS PRESSURE TEST BBENEDON Approved IVRS - Inspection :*
12/31/2013 ELECTRIC - SERVICE UPGRADE BBENEDON Approved IVRS - Inspection :*
12/31/2013 ELECTRIC - TEMPORARY SERVICE BBENEDON Approved IVRS - Inspection :*
01/02/2014 RIGHT OF WAY - FINAL PW Approved
01/02/2014 NPPO - FINAL RLEDONNE Approved
01/02/2014 SIGN - FINAL RLEDONNE Approved
02/13/2014 FIRE - ALARM FINAL CBASALDU Approved
02/27/2014 MECHANICAL - FINAL BBENEDON Approved IVRS - Inspection :*
02/27/2014 ELECTRIC - FINAL BBENEDON Approved IVRS - Inspection :*
02/28/2014 LANDSCAPE - FINAL RLEDONNE Approved
02/28/2014 ENGINEERING - FINAL RLEDONNE Approved
03/07/2014 PLUMBING - ROOF DRAINS BBENEDON Approved PER PLMB FINAL