Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 12/24/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
IVRS - Inspection :* |
| 11/18/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection :* |
| 11/18/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
FOOTINGS OK TO POUR |
| 10/14/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 10/02/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection :* |
| 10/02/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
OK TO POUR CENTER CMU PARTITION & PAD FOOTING FOR COLUMN WESTSIDE |
| 09/18/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection :* |
| 09/18/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
PHASE TWO FOOTINGS |
| 08/14/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection :* |
| 08/14/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
EASTSIDE OK |
| 08/13/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
IVRS - Inspection :* |
| 08/13/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
CANCELED |
| 07/23/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
IVRS - Inspection :* |
| 07/23/2013 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
EASTSIDE CONTINUOUS FOOTINGS - 2 COLUMN FOOTINGS - OK TO POUR PROGRESS AREAS |