Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Address:
504 E 9TH ST
Address NEW:
504 E 9TH ST
Apply Date:
12/19/2012
Applicant:
N/A
Description:
MULTI-FAMILY HOUSING
Architects:
  • MORROW, KEVIN THOMAS
Contractors:
  • ADOLFSON AND PETERSON CONSTRUCTION *C

Permit Reviews

Permit Number - T12CM08030
Permit Status: C of o
Permit Description: MULTI-FAMILY HOUSING
Start Date Submittal Complete Date Status  
03/24/2014 REVISION - - 4TH 04/03/2014 COMPLETED Review Details
05/02/2013 COMMERCIAL - NEW 05/24/2013 COMPLETED Review Details
05/24/2013 RESUBMITTAL 06/06/2013 COMPLETED Review Details
06/06/2013 RESUBMITTAL 06/26/2013 COMPLETED Review Details
06/26/2013 REVISION - - 1ST 07/03/2013 COMPLETED Review Details
08/19/2013 REVISION - - 2ND 08/20/2013 COMPLETED Review Details
08/20/2013 REVISION - - 2ND 09/12/2013 COMPLETED Review Details
10/03/2013 REVISION - - 3RD 10/03/2013 COMPLETED Review Details
12/19/2012 PLANS OK TO SUBMIT - COMM 12/19/2012 COMPLETED Review Details
12/19/2012 COMMERCIAL - NEW 05/02/2013 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T12CM08030
Permit Description: MULTI-FAMILY HOUSING
Total Completed Inspections - 50
Date Description Inspector Results Comments
09/13/2013 ELECTRIC - TEMPORARY POLE DQUINN Approved
09/16/2013 TEP CLEARANCE - AM DQUINN Approved CLEAR TEMP POLE TMPP
09/19/2013 PLUMBING - SEWER HCS CONNECT RMYERS Approved 1. Sewer to second elevation change OK. 4" type "L" copper from meter set to stub up at Bldg. #02.
09/23/2013 PLUMBING - PRE SLAB DQUINN Approved
11/25/2013 EXCAVATION/LAYOUT REBAR & ZON DQUINN Approved SOUTH SIDE EAST AND WEST GRADE BEAMS AND SLURRY WALLS OK
11/27/2013 PLUMBING - ROUGH, SOIL DQUINN Approved 6" SEWER LINE AIR TESTED FROM WEST MAN HOLE TO NORTH AND TO SOUTH BUILDINGS OK
6" SEWER FROM NORTH MANHOLE TO NORTH BUILDING AIR TESTED AND OK
12/03/2013 ELECTRIC - UNDERGROUND DQUINN Approved UNDERGROUND CONDUITS TO THE NORTH, WEST AND
SOUTH OF THE SOUTH ELEVATOR SHAFT OK TO BURY
12/03/2013 ROOF NAILING DQUINN Approved AMENITY BUILDING ROOF OK TO DRY IN
12/10/2013 FIRE SPKLR - UG, PIPING, HYDRO CSCHULTZ Approved 200 PSI for 2 hours
12/11/2013 BUILDING PRE-SLAB DQUINN Approved SOUTH FIRE RISER ROOM SLAB OK TO POUR.
SOUTH DUMPSTER SLAB OK TO POUR.
12/11/2013 REINFORCED MASONRY PRE-GROUT DQUINN Approved SOUTH PROPERTY WALL OK TO GROUT TO 4'8" ON 12/9.
SOUTH PROPERTY WALL OK TO GROUT TO BOND BEAM ON 12/10.
12/20/2013 PLUMBING - INTERMEDIATE DQUINN Approved 1ST FLOOR AMENITIES AND UNIT 103 DWV OK
12/30/2013 STUCCO MESH DQUINN Approved NORTH SIDE OF AMENITIES BUILDING OK TO STUCCO
12/30/2013 EXT METAL CLIPS/EXT SHEATHING DQUINN Approved 1ST FLOOR OF WEST WING- BOTH BUILDING 1 + 2, EXTERIOR OSB HAS SEVERAL AREAS TO RENAIL. LIST OF PARTICULAR AREAS WAS GIVEN TO FRAMING FORMAN.
03/19/2014 FIREWALL/FIREBARRIER/FIRESTOP DQUINN Approved FIRE STOP IN 306 -310 AND 406 -410 OK TO COVER
04/10/2014 FIRE SPKLR - UG PIPING FLUSH CBASALDU Approved
05/05/2014 FRAMING DQUINN Approved ALL FRAMING UP AND THROUGH UNIT #421 OK
06/17/2014 MECHANICAL - PROGRESS DQUINN Approved
06/17/2014 MECHANICAL - ABOVE CEILING DQUINN Approved
06/17/2014 MECHANICAL - INTERMEDIATE DQUINN Approved
06/17/2014 PLUMBING - PROGRESS DQUINN Approved
06/17/2014 PLUMBING - YARD WTR LINE/TEST DQUINN Approved
06/17/2014 PLUMBING - ABOVE CEILING DQUINN Approved
06/17/2014 ELECTRIC - PROGRESS DQUINN Approved
06/17/2014 ELECTRIC - ABOVE CEILING DQUINN Approved
06/17/2014 ELECTRIC - INTERMEDIATE DQUINN Approved
06/17/2014 ELECTRIC - UFER DQUINN Approved
06/17/2014 SHEET ROCK NAILING DQUINN Approved
06/17/2014 STEM WALL/RETAINING WALL DQUINN Approved
06/17/2014 U VALUE FOR WINDOW DQUINN Approved
06/20/2014 FIRE - ALARM FINAL WMOTTO Approved
06/20/2014 FIRE SPKLR - OH PIPING & HYDRO WMOTTO Approved
06/27/2014 FIRE SPKLR - FINAL CBASALDU Approved
07/08/2014 FIRE - FINAL CBASALDU Approved
07/21/2014 ELECTRIC - FINAL DQUINN Approved
07/21/2014 PLUMBING - FINAL DQUINN Approved
07/21/2014 MECHANICAL - FINAL DQUINN Approved
07/21/2014 PLUMBING - ROOF DRAINS DQUINN Approved
07/21/2014 BUILDING - PROGRESS DQUINN Approved
07/21/2014 BUILDING ABOVE CEILING DQUINN Approved
07/31/2014 FIRE - LANE SIGNS wmotto Approved
07/31/2014 FIRE - HYDRANTS wmotto Approved
07/31/2014 BUILDING - FINAL DQUINN Approved
07/31/2014 ELECTRIC - OUTDOOR LIGHTING DQUINN Approved
08/01/2014 RIGHT OF WAY - FINAL TWOLFGAN Approved
08/01/2014 ZONING - FINAL pyg Approved Compliance with IPP confirmed.
08/01/2014 LANDSCAPE - FINAL MRUSSO Approved
08/01/2014 SIGN - FINAL MRUSSO Approved
08/01/2014 NPPO - FINAL MRUSSO Approved
08/01/2014 ENGINEERING - FINAL MRUSSO Approved