Date Description Inspector Results Comments
06/17/2014 PLUMBING - INTERMEDIATE Approved
05/05/2014 PLUMBING - INTERMEDIATE Partial Approval ALL PLUMBING INTERMEDIATE COMPONANTS OK UP AND THROUGH UNIT #421
03/12/2014 PLUMBING - INTERMEDIATE Partial Approval PLUMB IN 406 - 410 OK
03/11/2014 PLUMBING - INTERMEDIATE Partial Approval PLUMB IN 306 - 310 OK
03/03/2014 PLUMBING - INTERMEDIATE Partial Approval DWV AND H20 IN AMENITIES 3RD AND 4TH FLOOR OK
DWV AND H20 IN 106 - 110 OK
02/20/2014 PLUMBING - INTERMEDIATE Partial Approval 3RD AND 4TH FLOOR OF AMENITIES BUILDING OK TO COVER
02/12/2014 PLUMBING - INTERMEDIATE Partial Approval DWV AND H20 OK TO COVER IN 302, 304, 402, 404
02/11/2014 PLUMBING - INTERMEDIATE Partial Approval H2O AND DWV OK IN 301 AND 401
02/07/2014 PLUMBING - INTERMEDIATE Partial Approval DWV AND SUPPLY OK IN UNITS 205 AND 204
01/24/2014 PLUMBING - INTERMEDIATE Partial Approval UNITS 201 +203 ARE READY FOR INSULATION AND ROCK
01/13/2014 PLUMBING - INTERMEDIATE Partial Approval 1ST AND 2ND FLOOR OF AMENITIES OK TO COVER
12/20/2013 PLUMBING - INTERMEDIATE Partial Approval 1ST FLOOR AMENITIES AND UNIT 103 DWV OK
12/18/2013 PLUMBING - INTERMEDIATE Not ready for Inspection DWV ON AMENITIES BUILDING NR DUE TO BLOWN TEST BALLS