Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T12CM06560
Permit Details
Apply Date:
10/18/2012
Applicant:
METRO TUCSON EXPEDITING & DEVELOPMENT
Description:
MEDICAL OFFICE
Architects:
- EGLIN, EVAN SAR
Contractors:
- EPSTEIN CONSTRUCTION L L C
Permit Reviews
Permit Number - T12CM06560
Permit Status: C of o
Permit Description: MEDICAL OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/18/2012 | COMMERCIAL - TI | 10/23/2012 | COMPLETED |
10/23/2012 | COMMERCIAL - TI | 11/06/2012 | COMPLETED |
11/06/2012 | RESUBMITTAL | 11/08/2012 | COMPLETED |
11/08/2012 | RESUBMITTAL | 11/14/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM06560
Permit Status: C of o
Permit Description: MEDICAL OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/18/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM06560
Permit Description: MEDICAL OFFICE
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/28/2012 | FRAMING | JMILITEL | Approved | OK TO TAPE ONE SIDED WALLS |
12/03/2012 | PLUMBING - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
12/05/2012 | PLUMBING - PRE SLAB | RMORENO | Approved | IVRS - Inspection :* |
12/05/2012 | PLUMBING - ROUGH, SOIL | RMORENO | Approved | IVRS - Inspection :* |
12/10/2012 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
12/20/2012 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* Provide access doors for fire dampers. Support expansion tank. Insulate hot water piping. Closet flanges ok. Corridors still need lights. Will chack corrections. Ok for ceiling tiles in rooms, leave out in corridors. |
12/20/2012 | PLUMBING - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
12/20/2012 | ELECTRIC - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
12/20/2012 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
12/28/2012 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
12/28/2012 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :*CHLORINATION REPORT OK NEED FIRE DAMPER TEST REPORT AND AIR BALANCE |
12/28/2012 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
12/31/2012 | PLUMBING - PROGRESS | JMILITEL | Approved | OK PER PLUMBING FINAL |
12/31/2012 | ELECTRIC - INTERMEDIATE | JMILITEL | Approved | OK PER ELECTRIC FINAL |
12/31/2012 | BUILDING - FINAL | DQUINN | Approved | |
12/31/2012 | SHEET ROCK NAILING | DQUINN | Approved | |
12/31/2012 | FIRE - FINAL | CBASALDU | Approved | 1. TCO until next week when FACP arrives. |
12/31/2012 | FIRE - ALARM FINAL | CBASALDU | Approved | 1. Need to test smokes with new FACP |
12/31/2012 | FIRE SPKLR - FINAL | CBASALDU | Approved | |
12/31/2012 | NPPO - FINAL | DROBERTS | Approved | |
12/31/2012 | SIGN - FINAL | DROBERTS | Approved | |
12/31/2012 | LANDSCAPE - FINAL | DROBERTS | Approved | |
12/31/2012 | ENGINEERING - FINAL | DROBERTS | Approved | |
12/31/2012 | RIGHT OF WAY - FINAL | P.Whiddon | Approved |