Permit: T12CM06399
Permit Details
Apply Date:
10/11/2012
Applicant:
BOHN, STEPHEN CHARLES
Description:
NEW OFFICE BLDG
Architects:
- BOHN, STEPHEN CHARLES
Contractors:
- RASCH CONSTRUCTION INC
Permit Reviews
Permit Number - T12CM06399
Permit Status: C of o
Permit Description: NEW OFFICE BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/30/2013 | RESUBMITTAL | 02/05/2013 | COMPLETED |
| 03/01/2013 | RESUBMITTAL | 03/26/2013 | COMPLETED |
| 08/21/2013 | OTHER | 08/21/2013 | COMPLETED |
| 10/11/2012 | PLANS OK TO SUBMIT - COMM | 10/11/2012 | COMPLETED |
| 10/16/2012 | COMMERCIAL - NEW | 01/30/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM06399
Permit Status: C of o
Permit Description: NEW OFFICE BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/11/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM06399
Permit Description: NEW OFFICE BLDG
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/26/2013 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | PVC DWV INSTALLED, OK. PLAN SPECS ABS |
| 07/26/2013 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 07/31/2013 | BUILDING PRE-SLAB | JBURGE | Approved | OK TO POUR SLAB |
| 07/31/2013 | PLUMBING - PRE SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 07/31/2013 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* |
| 08/26/2013 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 08/27/2013 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
| 08/29/2013 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | IVRS - Inspection :* |
| 08/29/2013 | PLUMBING - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 08/29/2013 | PLUMBING - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 08/30/2013 | PLUMBING - GAS PRESSURE TEST | JBURGE | Approved | IVRS - Inspection :* |
| 09/03/2013 | PLUMBING - SEWER HCS CONNECT | JBURGE | Approved | IVRS - Inspection :* |
| 09/09/2013 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 09/09/2013 | ELECTRIC - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 09/17/2013 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
| 09/23/2013 | SHEET ROCK NAILING | JBURGE | Approved | OK TO TAPE THROUGHOUT |
| 09/23/2013 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 10/03/2013 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | TRASH ENCLOSURE FOOTING - OK TO POUR |
| 10/03/2013 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* |
| 10/10/2013 | ELECTRIC - TEMPORARY SERVICE | JBURGE | Approved | |
| 10/10/2013 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
| 10/11/2013 | TEP CLEARANCE - AM | JBURGE | Approved | TMPP |
| 10/15/2013 | ELECTRIC - UNDERGROUND | JBURGE | Approved | 6"CONDUIT FROM TRANSFORMER TO BUILDING - OK TO COVER |
| 10/15/2013 | ELECTRIC - UNDERGROUND | JBURGE | Approved | IVRS - Inspection :* |
| 10/16/2013 | U VALUE FOR WINDOW | JBURGE | Approved | FACTOR AT 0.52 |
| 10/16/2013 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 10/16/2013 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
| 10/18/2013 | MECHANICAL - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 10/18/2013 | ELECTRIC - ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 10/31/2013 | ELECTRIC - UFER | RMOREN | Approved | |
| 10/31/2013 | MECHANICAL - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 10/31/2013 | PLUMBING - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 10/31/2013 | PLUMBING - PROGRESS | RMORENO | Approved | IVRS - Inspection :* |
| 10/31/2013 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 10/31/2013 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 10/31/2013 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
| 12/09/2013 | FIRE - FINAL | CSCHULTZ | Approved | |
| 12/10/2013 | BUILDING - PROGRESS | JBURGE | Approved | |
| 12/10/2013 | BUILDING ABOVE CEILING | JBURGE | Approved | |
| 12/10/2013 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 12/10/2013 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 12/16/2013 | RIGHT OF WAY - FINAL | JC | Approved | |
| 12/17/2013 | NPPO - FINAL | MRUSSO | Approved | NO WAY TO VERIFY NPPO PLAN WAS FOLLOWED, NEED CERT STATEMENT FROM LANDSCAPE ARCH. |
| 12/17/2013 | SIGN - FINAL | MRUSSO | Approved | NO INSPECTIONS CALLED IN, SIGNS WILL BE INSPECTED UNDER A SEPARATE PERMIT |
| 12/17/2013 | LANDSCAPE - FINAL | MRUSSO | Approved | PARTIAL APPROVAL, FINAL APPROVAL NOT TO BE GIVEN UNTIL ALL LANDSCAPING IS COMPLETED PER THE APPROVED PLAN AND A CERTIFICATION STATEMENT FROM THE LANDSCAPE ARCHITECT IS PROVIDED. |
| 12/17/2013 | ENGINEERING - FINAL | MRUSSO | Approved | PARTIAL APPROVAL, FINAL NOT TO BE GIVEN UNTIL ALL ITEMS IDENTIFIED UNDER PERMIT# DP12-0104 ARE COMPLETED AND APPROVED. |