Permit: T12CM03807
Permit Details
Apply Date:
06/26/2012
Applicant:
CARHUFF, PHILIP ANDREW
Description:
CHARTER SCHOOL
Architects:
- CARHUFF, PHILIP ANDREW
Contractors:
- CANYON BUILDING AND DESIGN LLC *APA*
Permit Reviews
Permit Number - T12CM03807
Permit Status: C of o
Permit Description: CHARTER SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/26/2012 | COMMERCIAL - TI | 06/29/2012 | COMPLETED |
| 06/29/2012 | COMMERCIAL - TI | 07/09/2012 | COMPLETED |
| 07/09/2012 | RESUBMITTAL | 07/10/2012 | COMPLETED |
| 07/23/2012 | REVISION - - 1ST | 07/23/2012 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T12CM03807
Permit Status: C of o
Permit Description: CHARTER SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/26/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM03807
Permit Description: CHARTER SCHOOL
Total Completed Inspections - 28
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/12/2012 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
| 07/12/2012 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 07/20/2012 | ELECTRIC - UFER | RMYERS | Approved | IVRS - Inspection :* |
| 07/23/2012 | PLUMBING - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 07/23/2012 | PLUMBING - INTERMEDIATE | MPUGH | Approved | IVRS - Inspection :* |
| 07/24/2012 | ELECTRIC - SERVICE UPGRADE | MPUGH | Approved | IVRS - Inspection :* |
| 07/25/2012 | TEP CLEARANCE - AM | MPUGH | Approved | |
| 07/27/2012 | SHEET ROCK NAILING | JMILITEL | Approved | IVRS - Inspection :* |
| 08/01/2012 | MECHANICAL - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 08/01/2012 | ELECTRIC - ABOVE CEILING | MPUGH | Approved | IVRS - Inspection :* |
| 08/02/2012 | MECHANICAL - FINAL | MPUGH | Approved | IVRS - Inspection :* |
| 08/03/2012 | FIRE - FINAL | WMOTTO | Approved | |
| 08/03/2012 | FIRE - ALARM FINAL | WMOTTO | Approved | |
| 08/03/2012 | FIRE SPKLR - FINAL | WMOTTO | Approved | |
| 08/03/2012 | RIGHT OF WAY - FINAL | TADKINS | Approved | |
| 08/03/2012 | NPPO - FINAL | DROBERTS | Approved | |
| 08/03/2012 | SIGN - FINAL | DROBERTS | Approved | |
| 08/03/2012 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 08/03/2012 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 08/03/2012 | ELECTRIC - INTERMEDIATE | MPUGH | Approved | |
| 08/03/2012 | ELECTRIC - UNDERGROUND | MPUGH | Approved | |
| 08/03/2012 | PLUMBING - PROGRESS | MPUGH | Approved | |
| 08/03/2012 | MECHANICAL - INTERMEDIATE | MPUGH | Approved | |
| 08/03/2012 | BUILDING ABOVE CEILING | MPUGH | Approved | |
| 08/03/2012 | FRAMING | MPUGH | Approved | |
| 08/03/2012 | BUILDING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
| 08/03/2012 | PLUMBING - FINAL | MPUGH | Approved | IVRS - Inspection :* |
| 08/03/2012 | ELECTRIC - FINAL | MPUGH | Approved | IVRS - Inspection :* |