Permit: T12CM01293
Permit Details
Apply Date:
03/22/2012
Applicant:
DANIEL SALEET
Description:
NEW 51,940 S.F. BUILDING W/CANOPY
Contractors:
- OLTMANS CONSTRUCTION CO ,
Permit Reviews
Permit Number - T12CM01293
Permit Status: C of o
Permit Description: NEW 51,940 S.F. BUILDING W/CANOPY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/22/2012 | PLANS OK TO SUBMIT - COMM | 03/22/2012 | COMPLETED |
| 03/22/2012 | COMMERCIAL - NEW | 05/11/2012 | COMPLETED |
| 05/11/2012 | RESUBMITTAL - TI ALL | 06/20/2012 | COMPLETED |
| 06/18/2012 | RESUBMITTAL | 06/26/2012 | COMPLETED |
| 06/26/2012 | RESUBMITTAL | 07/02/2012 | COMPLETED |
| 07/27/2012 | REVISION - - 1ST | 08/01/2012 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T12CM01293
Permit Description: NEW 51,940 S.F. BUILDING W/CANOPY
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/19/2012 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 09/27/2012 | PLUMBING - SEWER HCS CONNECT | DSANTACR | Approved | IVRS - Inspection :* |
| 09/27/2012 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
| 09/28/2012 | TEP CLEARANCE - AM | DSANTACR | Approved | OK TO CLEAR TEC COMM |
| 10/18/2012 | SHEET ROCK NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 10/22/2012 | STEM WALL/RETAINING WALL | RCAMACHO | Approved | IVRS - Inspection :* |
| 10/22/2012 | BUILDING PRE-SLAB | RCAMACHO | Approved | IVRS - Inspection :* |
| 10/22/2012 | EXCAVATION/LAYOUT REBAR & ZON | RCAMACHO | Approved | IVRS - Inspection :* |
| 10/22/2012 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 10/22/2012 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 10/22/2012 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 10/24/2012 | FIRE SPKLR - UG, PIPING, HYDRO | CSCHULTZ | Approved | |
| 10/28/2012 | FIRE SPKLR - UG PIPING FLUSH | CSCHULTZ | Approved | |
| 11/07/2012 | OUTDOOR LIGHTING FINAL | Ray Camacho | Approved | Finaled approved by R Camacho |
| 11/07/2012 | NPPO - FINAL | DROBERTS | Approved | |
| 11/07/2012 | SIGN - FINAL | DROBERTS | Approved | |
| 11/07/2012 | LANDSCAPE - FINAL | DROBERTS | Approved | |
| 11/07/2012 | ZONING - FINAL | DROBERTS | Approved | ZONING FINAL IS NOT TO BE GIVEN UNTIL THE CHAINLINK FENCE ON THE WEST SIDE OF THE PROJECT ADJACENT TO THE STATES RIGHT OF WAY IS REPAIRED AND APPROVED BY THEIR INSPECTORS. CONTACT SYLVIA HANNA AT THE PERMIT OFFICE FOR A.D.O.T. ON 22ND STREET AT THE DISTRICT ENGINEERING OFFICE. |
| 11/07/2012 | ENGINEERING - FINAL | DROBERTS | Approved | |
| 11/07/2012 | PLUMBING - FINAL | RCAMACHO | Approved | 1) ADA SIGNS INTERIOR 2) ADDRESSING FROM 22ND ST 3) COMPLETE HANDICAPPED PARKING 4) PROVIDE STERILIZATION REPORT 5) PROVIDE BALANCE REPORT |
| 11/07/2012 | FIRE - ALARM FINAL | CSCHULTZ | Approved | Have clean panel showing |
| 11/07/2012 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | FIX THE FUEL LEAK TO FIRE PUMP Brace all 21/2" hose connections Install inspectors test valve on riser #1 by battery charging station Label all tamper valves per the call out on the fire panel Sign the riser room door Have a clean fire panel showing no problems Install tampers for the outside OS&Y's for sprinkler system. Fix water leaks on supply line to sprinkler system outside by the OSY valve. |
| 11/07/2012 | ELECTRIC - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 11/08/2012 | RIGHT OF WAY - FINAL | TWOLFGAN | Approved | |
| 11/08/2012 | HEALTH DEPT - FINAL 724-7908 | NRAMIREZ | Approved | |
| 11/08/2012 | PLUMBING - PROGRESS | RCAMACHO | Approved | |
| 11/08/2012 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | |
| 11/08/2012 | PLUMBING - ROOF DRAINS | RCAMACHO | Approved | |
| 11/08/2012 | PLUMBING - ABOVE CEILING | RCAMACHO | Approved | |
| 11/08/2012 | PLUMBING - PRE SLAB | RCAMACHO | Approved | |
| 11/08/2012 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | |
| 11/08/2012 | ELECTRIC - OUTDOOR LIGHTING | RCAMACHO | Approved | |
| 11/08/2012 | ELECTRIC - PROGRESS | RCAMACHO | Approved | |
| 11/08/2012 | ELECTRIC - CABLE DROP | RCAMACHO | Approved | |
| 11/08/2012 | ELECTRIC - ABOVE CEILING | RCAMACHO | Approved | |
| 11/08/2012 | ELECTRIC - UNDERGROUND | RCAMACHO | Approved | |
| 11/08/2012 | MECHANICAL - FINAL | RCAMACHO | Approved | |
| 11/08/2012 | ELECTRIC - SERVICE UPGRADE | RCAMACHO | Approved | |
| 11/08/2012 | BUILDING - PROGRESS | RCAMACHO | Approved | |
| 11/08/2012 | U VALUE FOR WINDOW | RCAMACHO | Approved | |
| 11/08/2012 | BUILDING ABOVE CEILING | RCAMACHO | Approved | |
| 11/08/2012 | FRAMING | RCAMACHO | Approved | |
| 11/29/2012 | FIRE - FINAL | TKNAPP | Approved | APPROVED |
| 11/30/2012 | BUILDING - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 01/08/2013 | FIRE - LANE SIGNS | kb | Approved | |
| 01/08/2013 | FIRE - HYDRANTS | kb | Approved |