| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/29/2012 | FIRE - FINAL | Approved | APPROVED | |
| 11/07/2012 | FIRE - FINAL | Partial Approval | Temp C of O Approved FIX THE FUEL LEAK TO FIRE PUMP Brace all 21/2" hose connections Install inspectors test valve on riser #1 by battery charging station Label all tamper valves per the call out on the fire panel Sign the riser room door Have a clean fire panel showing no problems Install tampers for the outside OS&Y's for sprinkler system. Fix water leaks on supply line to sprinkler system outside by the OSY valve. |
|
| 11/05/2012 | FIRE - FINAL | Denied | Need tampers on outside OS&Y's. Brace inspectors test valve for canopy area. Brace all 2 1/2" hose connections Install inspector test valve for riser #1 by battery station Install riser room sign on riser door |
|
| 11/05/2012 | FIRE - FINAL | Denied | Need tampers on outside OS&Y's. Brace inspectors test valve for canopy area. Brace all 2 1/2" hose connections Install inspector test valve for riser #1 by battery station Install riser room sign on riser door |