Permit: T12CM00073
Permit Details
Apply Date:
01/11/2012
Applicant:
WAYNE SILBERSCHLAG
Description:
NEW 14,500 S.F. STRIP SHOPPING CENTER SHELL BLDG
Architects:
- SILBERSCHLAG, WAYNE DAVID
Contractors:
- W.E.O'NEIL CONSTRUCTION CO. INC
Permit Reviews
Permit Number - T12CM00073
Permit Status: Final
Permit Description: NEW 14,500 S.F. STRIP SHOPPING CENTER SHELL BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/11/2012 | PLANS OK TO SUBMIT - COMM | 01/11/2012 | COMPLETED |
| 01/11/2012 | COMMERCIAL - NEW | 01/30/2012 | COMPLETED |
| 02/23/2012 | RESUBMITTAL - TI ALL | 05/16/2012 | COMPLETED |
| 08/29/2012 | REVISION - - 1ST | 10/15/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12CM00073
Permit Status: Final
Permit Description: NEW 14,500 S.F. STRIP SHOPPING CENTER SHELL BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/11/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T12CM00073
Permit Description: NEW 14,500 S.F. STRIP SHOPPING CENTER SHELL BLDG
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/19/2012 | NPPO PRE PERMIT INSPECTION | MRUSSO | Approved | NPPO: 1) ADD TWO OCCOTILLO'S DURING THE LANDSCAPING PHASE IN ORDER TO REPLACE THE ONES SHOWN ON THE NPPO PLAN THAT ARE MISSING. 2) EXISTING OLIVE TREES PLANTED ALONG THE SOUTH SIDE OF THE PROJECT ARE IN THE RIGHT-OF-WAY. THE CONTRACTOR WILL LANDSCAPE WITH DESERT PLANTS FROM THE PROPERTY LINE IN. THE CONTRACTOR ASKED IF THE OLIVE TREES CAN BE REMOVED. 3) DATE PALM TREES ALONG THE SOUTH SIDE OF THE BLDG WILL BE MOVED AND RE-PLANTED |
| 05/19/2012 | ENGINEERING PRE-CONSTRUCTION | MRUSSO | Approved | SWPPP: 1) INSTALL SEDIMENT CONTROLS AS SHOWN ON APPROVED STORM WATER PLAN. 2) POST A COPY OF YOUR SIGNED NOI ON SITE. 3) INSTALL A STABILIZED CONSTRUCTION ENTRANCE OR ENTRANCES AT ALL ROUTES TO AND FROM THE SITE AS SHOWN ON THE APPROVED STORM WATER PLAN. 4) INSTALL A CONCRETE WASH OUT WHEN APPLICABLE. 5) SHOW ANY AND ALL CHANGES MADE TO THE APPROVED STORM WATER PLAN. 6) ENSURE TO PERFOM STORM WATER SELF INSPECTION AS REQUIRED UNDER YOUR PLAN. INSPECTIONS MUST BE DOCUMENTED. NPPO: 1) ADD TWO OCCOTILLO'S DURING THE LANDSCAPING PHASE IN ORDER TO REPLACE THE ONES SHOWN ON THE NPPO PLAN THAT ARE MISSING. 2) EXISTING OLIVE TREES PLANTED ALONG THE SOUTH SIDE OF THE PROJECT ARE IN THE RIGHT-OF-WAY. THE CONTRACTOR WILL LANDSCAPE WITH DESERT PLANTS FROM THE PROPERTY LINE IN. THE CONTRACTOR ASKED IF THE OLIVE TREES CAN BE REMOVED. 3) DATE PALM TREES ALONG THE SOUTH SIDE OF THE BLDG WILL BE MOVED AND RE-PLANTED |
| 07/06/2012 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* |
| 07/16/2012 | STEM WALL/RETAINING WALL | RHOLLAND | Approved | IVRS - Inspection :* |
| 08/07/2012 | PLUMBING - ROUGH, SOIL | RHOLLAND | Approved | OK FOR GREASE TRAP RON |
| 09/27/2012 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | OK GROUND RODS +4 PVC AT SES SLAB |
| 10/23/2012 | BUILDING PRE-SLAB | DQUINN | Approved | B,C & D RISER ROOM & N FACE OF A OK POUR |
| 10/23/2012 | ROOF NAILING | DQUINN | Approved | IVRS - Inspection :* |
| 11/02/2012 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | |
| 11/02/2012 | ENGINEERING - FINAL | RLEDONNE | Approved | |
| 11/08/2012 | PLUMBING - YARD WTR LINE/TEST | RHOLLAND | Approved | IVRS - Inspection :* |
| 11/13/2012 | SHEET ROCK NAILING | DQUINN | Approved | PAD 1 E&W SIGN PLY OK |
| 11/18/2012 | FIRE SPKLR - OH PIPING & HYDRO | CBASALDU | Approved | |
| 11/28/2012 | FRAMING | RHOLLAND | Approved | OK FRONT SOFFIT AND CANS IN SOFFIT |
| 11/28/2012 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | Will need riser room door label "RISER ROOM" and install a FD key box for access. |
| 11/28/2012 | FIRE SPKLR - UG PIPING FLUSH | CSCHULTZ | Approved | FLUSHED FOR 3 MINS |
| 11/28/2012 | FIRE SPKLR - UG, PIPING, HYDRO | CSCHULTZ | Approved | 200 PSI FOR HOURS |
| 11/28/2012 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/11/2012 | STUCCO MESH | JMILITEL | Approved | IVRS - Inspection :* |
| 12/11/2012 | EXCAVATION/LAYOUT REBAR & ZON | JMILITEL | Approved | IVRS - Inspection :* |
| 12/28/2012 | REINFORCED MASONRY PRE-GROUT | JMILITEL | Approved | IVRS - Inspection :*OK TO GROUT SCREEN WALL AT SW CORNER OF BLDG |
| 01/02/2013 | EXT METAL CLIPS/EXT SHEATHING | JMILITEL | Approved | IVRS - Inspection :* |
| 01/02/2013 | PLUMBING - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 01/02/2013 | PLUMBING - PRE SLAB | JMILITEL | Approved | IVRS - Inspection :* |
| 01/07/2013 | ELECTRIC - TEMPORARY SERVICE | JMILITEL | Approved | IVRS - Inspection :* |
| 01/07/2013 | BUILDING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 01/07/2013 | BUILDING ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
| 01/07/2013 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 01/07/2013 | PLUMBING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 01/07/2013 | PLUMBING - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 01/07/2013 | PLUMBING - ROOF DRAINS | JMILITEL | Approved | IVRS - Inspection :* |
| 01/07/2013 | ELECTRIC - PROGRESS | JMILITEL | Approved | IVRS - Inspection :* |
| 01/16/2013 | ELECTRIC - TEMP POWER FOR TEST | JMILITEL | Approved | IVRS - Inspection :* |
| 01/16/2013 | ELECTRIC - CABLE DROP | JMILITEL | Approved | IVRS - Inspection :* |
| 01/16/2013 | U VALUE FOR WINDOW | JMILITEL | Approved | IVRS - Inspection :* |
| 01/16/2013 | ELECTRIC - OUTDOOR LIGHTING | JMILITEL | Approved | IVRS - Inspection :* |
| 01/17/2013 | TEP CLEARANCE - AM | JMILITEL | Approved | OK TO CLEAR COMMERCIAL ECO HOUSE PANEL 1 METER |
| 01/17/2013 | NPPO - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 01/17/2013 | SIGN - FINAL | RLEDONNE | Approved | NA TO THIS ACTIVITY. |
| 01/18/2013 | RIGHT OF WAY - FINAL | P.Whiddon | Approved | |
| 01/22/2013 | BUILDING - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 01/22/2013 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 01/22/2013 | OUTDOOR LIGHTING FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 01/22/2013 | ELECTRIC - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 01/23/2013 | FIRE - FINAL | CSCHULTZ | Approved | |
| 02/19/2013 | LANDSCAPE - FINAL | RLEDONNE | Approved |