Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T12CM00073

Parcel: 12709016A


Addresses:

5545 E BROADWAY BL

Inspection Status: Approved

Inspection History: ENGINEERING PRE-CONSTRUCTION

Date Description Inspector Results Comments
05/19/2012 ENGINEERING PRE-CONSTRUCTION Approved SWPPP:
1) INSTALL SEDIMENT CONTROLS AS SHOWN ON APPROVED STORM WATER PLAN.
2) POST A COPY OF YOUR SIGNED NOI ON SITE.
3) INSTALL A STABILIZED CONSTRUCTION ENTRANCE OR ENTRANCES AT ALL ROUTES TO AND FROM THE SITE AS SHOWN ON THE APPROVED STORM WATER PLAN.
4) INSTALL A CONCRETE WASH OUT WHEN APPLICABLE.
5) SHOW ANY AND ALL CHANGES MADE TO THE APPROVED STORM WATER PLAN.
6) ENSURE TO PERFOM STORM WATER SELF INSPECTION AS REQUIRED UNDER YOUR PLAN. INSPECTIONS MUST BE DOCUMENTED.

NPPO:
1) ADD TWO OCCOTILLO'S DURING THE LANDSCAPING PHASE IN ORDER TO REPLACE THE ONES SHOWN ON THE NPPO PLAN THAT ARE MISSING.
2) EXISTING OLIVE TREES PLANTED ALONG THE SOUTH SIDE OF THE PROJECT ARE IN THE RIGHT-OF-WAY. THE CONTRACTOR WILL LANDSCAPE WITH DESERT PLANTS FROM THE PROPERTY LINE IN. THE CONTRACTOR ASKED IF THE OLIVE TREES CAN BE REMOVED.
3) DATE PALM TREES ALONG THE SOUTH SIDE OF THE BLDG WILL BE MOVED AND RE-PLANTED