Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - UG, PIPING, HYDRO
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/28/2012 | FIRE SPKLR - UG, PIPING, HYDRO | Approved | 200 PSI FOR HOURS | |
| 11/05/2012 | FIRE SPKLR - UG, PIPING, HYDRO | Denied | As stated in July 07, 2012 inspection you will need a separate plan and permit for underground work, I called sprinkler contractor Allen fire to call construction contractor and advised him that we will not be coming out until separate permit for underground is approved. | |
| 07/05/2012 | FIRE SPKLR - UG, PIPING, HYDRO | Denied | 1.) Looked at 6 foot stub out with 11 feet piping all ductile need to wrap all piping in PVC plastic with install tracer wire also 200 PSI test for 2 hours approved. 2.) Advise construction supervisor that they will need to get a separate approved plan and permit for the installation of the underground. |