Permit: T12BU00091
Permit Details
Apply Date:
01/19/2012
Applicant:
N/A
Description:
GRADING: BROOKSHIRE VILLAGE IMPROVEMENTS
Contractors:
- DIVISION II CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T12BU00091
Permit Status: Final
Permit Description: GRADING: BROOKSHIRE VILLAGE IMPROVEMENTS
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/19/2012 | PLANS OK TO SUBMIT - GRADING | 01/19/2012 | COMPLETED |
01/19/2012 | GRADING | 02/29/2012 | COMPLETED |
03/19/2012 | RESUBMITTAL - GRADING | 08/28/2012 | COMPLETED |
07/10/2015 | REVISION - GRADING | 07/16/2015 | COMPLETED |
09/18/2012 | REVISION - GRADING | 09/18/2012 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T12BU00091
Permit Status: Final
Permit Description: GRADING: BROOKSHIRE VILLAGE IMPROVEMENTS
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/19/2012 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T12BU00091
Permit Description: GRADING: BROOKSHIRE VILLAGE IMPROVEMENTS
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/20/2012 | ENGINEERING PRE-CONSTRUCTION | MRUSSO | Approved | 1) ENSURE SEDIMENT CONTROLS ARE INSTALLED PER THE APPROVED SWPPP 2) SWEEP UP TRACKED SOIL OFF PUBLIC ROADWAYS ON A ROUTINE BASIS. 3) CALL FOR RE-INSPECTION WHEN SEDIMENT CONTROLS HAVE BEEN INSTALLED OR IF YOU HAVE ANY CONCERNS OR CHANGES TO THE APPROVED PLANS. 4) ENSURE YOU PERFORM STORM WATER SELF INSPECTIONS PER YOUR PERMIT REQUIREMENT AND DOCUMENT THEM |
10/17/2012 | STORMWATER INSTALL OF CONTROLS | MRUSSO | Approved | 1) SEDIMENT CONTROLS HAVE BEEN INSTALLED ALONG THE PERIMETER OF THE SITE. 2) ENSURE SEDIMENT CONTROLS ARE INSPECTED AND MAINTAINED THROUGHOUT CONSTRUCTION. 3) PERFORM AND DOCUMENT STORM WATER SELF INSPECTIONS. 4) SWEEP UP TRACKED SOIL AS NEEDED 5) CALL FOR ANY CONCERNS AND/OR QUESTIONS W/ SITE WORK. |
12/05/2012 | STORMWATER FOLLOW-UP INSP | RUSSO | Approved | 1) MET WITH SUPERINTENDENT WALKED SITE. 2) INSPECTED HC ACCESS RAMP ALONG THE FRONT OF ACE HARDWARE. 3) PARKING AREA ALONG SW CORNER OF SITE HAS BEEN CPMPLETED. 4) NO STORM WATER CONCERNS AT THIS TIME |
12/17/2012 | GRADING - INTERMEDIATE | MRUSSO | Approved | LOOKED AT ENTRANCE TO BASKIN ROBBINS. CONTRACTOR INSTALLING A HC RAMP AND SIDE WALK. ENSURE SLOPES MEET APPLICABLE STANDARDS/CODES |
04/30/2013 | STORMWATER FINAL INSPECTION | MRUSSO | Approved | |
04/30/2013 | LANDSCAPE INSPECTION | MRUSSO | Approved | |
10/02/2015 | GRADING - CHECK FOR ACTIVITY | MRUSSO | Approved | |
10/02/2015 | GRADING - REBAR | MRUSSO | Approved | |
10/02/2015 | GRADING - FINAL | MRUSSO | Approved |