Permit Details

Status:
C of o
Type:
COMMERCIAL ADDITION
Address:
2450 E RIVER RD
Address NEW:
2450 E RIVER RD
Apply Date:
07/20/2011
Applicant:
CAYLOR CONSTRUCTION COMPANY , RO
Description:
CENTER FOR NEUROSCIENCES:OFFICE
Contractors:
  • CAYLOR CONSTRUCTION COMPANY , RO

Permit Reviews

Permit Number - T11CM02309
Permit Status: C of o
Permit Description: CENTER FOR NEUROSCIENCES:OFFICE
Start Date Submittal Complete Date Status  
07/20/2011 PLANS OK TO SUBMIT - COMM 07/21/2011 COMPLETED Review Details
07/21/2011 COMMERCIAL - NEW 08/04/2011 COMPLETED Review Details
08/08/2011 RESUBMITTAL 08/17/2011 COMPLETED Review Details
08/17/2011 RESUBMITTAL 08/17/2011 COMPLETED Review Details
09/01/2011 REVISION - - 1ST 09/01/2011 COMPLETED Review Details
09/19/2011 REVISION - - 2ND 09/27/2011 COMPLETED Review Details
11/08/2011 REVISION - - 3RD 11/10/2011 ACTIVE Review Details

Outstanding Activity Conditions

Permit Number - T11CM02309
Permit Status: C of o
Permit Description: CENTER FOR NEUROSCIENCES:OFFICE
Total Outstanding Activity Conditions - 1
Date Name
07/20/2011 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T11CM02309
Permit Description: CENTER FOR NEUROSCIENCES:OFFICE
Total Completed Inspections - 39
Date Description Inspector Results Comments
10/17/2011 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
1) FOR MINI SPLIT UNIT CONNECT OVERFLOW SENSOR AND PROVIDE 20 AMP FUSES FOR CONDENSOR
10/17/2011 ELECTRIC - FINAL RHOLLAND Approved IVRS - Inspection :*
10/20/2011 ZONING - FINAL LHANLY Approved D11-0023 HAS BEEN APPROVED
10/21/2011 RIGHT OF WAY - FINAL M.Otero Approved
10/25/2011 SIGN - FINAL MRUSSO Approved
10/25/2011 NPPO - FINAL MRUSSO Approved
11/08/2011 MECHANICAL - HYDRONIC PIPING JMILITEL Approved IVRS - Inspection :*
1) 100 PSI HYDRO TEST ON ALL UNDERGROUND PIPING OK TO COVER
11/17/2011 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
1) ABOVE CEILING CT ROOM OK
11/17/2011 ELECTRIC - ABOVE CEILING RHOLLAND Approved IVRS - Inspection :*
1) OK ROOM CT
11/18/2011 ELECTRIC - UNDERGROUND RHOLLAND Approved IVRS - Inspection :*
1) OK 20' #2 COPPER ATTACH TO REBAR
11/18/2011 ELECTRIC - UFER RHOLLAND Approved IVRS - Inspection :*
12/01/2011 ROOF NAILING JBURGE Approved IVRS - Inspection :*
1) OK TO DRY IN
12/02/2011 STEM WALL/RETAINING WALL JBURGE Approved IVRS - Inspection :*
1) NORTH EAST CORNER OF ROOM #129 OK TO POUR
12/16/2011 PLUMBING - ROOF DRAINS RMYERS Approved IVRS - Inspection :*
12/16/2011 PLUMBING - ROOF DRAINS RMYERS Approved IVRS - Inspection :*
12/16/2011 PLUMBING - INTERMEDIATE RMYERS Approved IVRS - Inspection :*
12/19/2011 EXT METAL CLIPS/EXT SHEATHING AQUIROZ Approved IVRS - Inspection :*
12/21/2011 U VALUE FOR WINDOW AQUIROZ Approved IVRS - Inspection :*
12/21/2011 STUCCO MESH AQUIROZ Approved IVRS - Inspection :*
12/21/2011 FRAMING AQUIROZ Approved IVRS - Inspection :*
12/21/2011 REINFORCED MASONRY PRE-GROUT AQUIROZ Approved IVRS - Inspection :*
12/21/2011 BUILDING PRE-SLAB AQUIROZ Approved IVRS - Inspection :*
12/21/2011 EXCAVATION/LAYOUT REBAR & ZON AQUIROZ Approved IVRS - Inspection :*
12/21/2011 PLUMBING - ABOVE CEILING RMYERS Approved IVRS - Inspection :*
12/21/2011 PLUMBING - PRE SLAB RMYERS Approved IVRS - Inspection :*
12/21/2011 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection :*
12/28/2011 SHEET ROCK NAILING RHOLLAND Approved IVRS - Inspection :*
1) OK WALLS ROOMS #102-116, 118-121, 125, 127, 101 AND 117 EAST SIDE
2) CHECK OFFICE WINDOWS
12/28/2011 ELECTRIC - INTERMEDIATE RHOLLAND Approved IVRS - Inspection :*
1) OK WALLS ROOMS #101, 102, 105, 106, 111, 116, 117, 120 AND EDF
01/23/2012 BUILDING - PROGRESS AQUIROZ Approved IVRS - Inspection :*
02/02/2012 PLUMBING - PROGRESS RMYERS Approved IVRS - Inspection :*
02/03/2012 BUILDING ABOVE CEILING AQUIROZ Approved IVRS - Inspection :*
02/10/2012 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
02/10/2012 FIRE - FINAL WMOTTO Approved
02/10/2012 FIRE SPKLR - FINAL WMOTTO Approved
03/09/2012 PLUMBING - FINAL RMYERS Approved IVRS - Inspection :*
03/13/2012 LANDSCAPE - FINAL MRUSSO Approved
03/13/2012 ENGINEERING - FINAL MRUSSO Approved
03/20/2012 BUILDING - FINAL AQUIROZ Approved IVRS - Inspection :*
1) NEED 27" KNEE CLEARANCE AT DRINKING FOUNTAIN 18" VERTICAL GRAB BAR MUST BE 39"-41" TO CENTER
03/20/2012 BUILDING - FINAL AQUIROZ Approved