Permit: T11CM02063
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
4230 N ORACLE RD #180
Address NEW:
4230 N ORACLE RD #180
Apply Date:
06/30/2011
Applicant:
MIKE HILLS
Description:
TI: RETAIL
Contractors:
- DOUBLE A A BUILDERS LTD ,
Permit Reviews
Permit Number - T11CM02063
Permit Status: C of o
Permit Description: TI: RETAIL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/30/2011 | PLANS OK TO SUBMIT - COMM | 06/30/2011 | COMPLETED |
| 06/30/2011 | COMMERCIAL - TI | 07/28/2011 | COMPLETED |
| 08/15/2011 | RESUBMITTAL - TI ALL | 09/15/2011 | COMPLETED |
| 09/26/2011 | REVISION - - 1ST | 09/26/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM02063
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 06/30/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM02063
Permit Description: TI: RETAIL
Total Completed Inspections - 26
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/20/2011 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1) ARCHITECT APPROVES ABS 2) WATER TEST ONE RISER TO 10' 3) OK TO BACKFILL |
| 09/20/2011 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 09/29/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 09/29/2011 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/05/2011 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/25/2011 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
| 10/27/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 10/27/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 10/28/2011 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR #180 PER R. HOLLANDER |
| 10/31/2011 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/01/2011 | FIRE SPKLR - FINAL | DSIWARSK | Approved | PER INSP CARD |
| 11/01/2011 | FIRE - FINAL | DSIWARSK | Approved | PER INSP CARD |
| 11/01/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 11/01/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 11/02/2011 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* 1) NEED ALL OTHER TRADES AND FIRE APPROVAL |
| 11/02/2011 | BUILDING ABOVE CEILING | AQUIROZ | Approved | PER BU FINAL |
| 11/02/2011 | BUILDING - FINAL | AQUIROZ | Approved | PER INSP CARD |
| 11/02/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | PER PL FINAL |
| 11/02/2011 | ELECTRIC - ABOVE CEILING | AQUIROZ | Approved | PER EL FINAL |
| 11/02/2011 | ELECTRIC - INTERMEDIATE | AQUIROZ | Approved | PER EL FINAL |
| 11/02/2011 | ELECTRIC - FINAL | AQUIROZ | Approved | PER INSP CARD |
| 11/03/2011 | NPPO - FINAL | MRUSSO | Approved | PER INSP CARD |
| 11/03/2011 | SIGN - FINAL | MRUSSO | Approved | PER INSP CARD |
| 11/03/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | PER INSP CARD |
| 11/03/2011 | RIGHT OF WAY - FINAL | RLEIGH | Approved | |
| 11/03/2011 | ENGINEERING - FINAL | RLEIGH | Approved |