Permit: T11CM01603
Permit Details
Apply Date:
05/25/2011
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW HIGH SCHOOL
Architects:
- SWAIM, PHILLIP ELLIOTT
Contractors:
- LLOYD CONSTRUCTION COMPANY INC ,
Permit Reviews
Permit Number - T11CM01603
Permit Status: C of o
Permit Description: NEW HIGH SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/25/2011 | PLANS OK TO SUBMIT - COMM | 05/25/2011 | COMPLETED |
| 05/25/2011 | COMMERCIAL - NEW | 06/15/2011 | COMPLETED |
| 06/24/2011 | RESUBMITTAL | 07/20/2011 | COMPLETED |
| 07/21/2011 | RESUBMITTAL | 07/29/2011 | COMPLETED |
| 07/29/2011 | RESUBMITTAL | 08/01/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM01603
Permit Status: C of o
Permit Description: NEW HIGH SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/25/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM01603
Permit Description: NEW HIGH SCHOOL
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/25/2011 | ELECTRIC - UFER | JBURGE | Approved | IVRS - Inspection :* 1) APPROVED AS PER NEC 2011 250.52 (3) |
| 11/08/2011 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* 1) 4 COLUMN FOOTINGS (C5/F8); 1 C5/F6; 2 WALL FOOTINGS (F3/W6) AS PER DETAIL #125A OK TO POUR PROGRESS AREAS |
| 11/21/2011 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
| 11/21/2011 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
| 11/30/2011 | PLUMBING - YARD WTR LINE/TEST | JBURGE | Approved | IVRS - Inspection :* |
| 12/06/2011 | FIRE SPKLR - UG PIPING FLUSH | CSCHULTZ | Approved | 10" stainless steel stub and 10' C-PVC with bolt clamps and thrust block approved okay to bury. Need separate plan and permit for sprinkler and underground piping for fire systems need separate for all systems that are checked off on front of approved plans. |
| 12/09/2011 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* 1) 201, 202, 203 AND 204 UNDERGROUND IN BLDG OK 2) SIGN GATE OK STUBS 3) 206 UNDERGROUND OK 4) 205, 207, 208, 209 AND ELECTRICAL ROOM OK 5) MDF ROOM TOWARDS PANTANO UNDERGROUND OK |
| 12/27/2011 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* 1) ROOMS #112, 115, 118, 119, 205, 206, 210 HAVE #3 REBAR 2' ON CENTER 2) RFI'S, REBAR, VAPOR BARRIER AND DOWELS INSTALLED AT DOORWAYS AT A LATER DATE |
| 12/28/2011 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
| 03/08/2012 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO DRY IN BLDGS |
| 03/27/2012 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 03/30/2012 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 04/20/2012 | FIRE SPKLR - OH PIPING & HYDRO | WMOTTO | Approved | |
| 04/20/2012 | FIRE SPKLR - UG, PIPING, HYDRO | WMOTTO | Approved | |
| 05/21/2012 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SET CEILING TILES |
| 05/21/2012 | MECHANICAL - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* 1) STAMPED RFI FOR CHANGES TO FLEX CONNECTORS AND SOUND PLENIUM FROM KC MECH |
| 05/21/2012 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 05/21/2012 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 06/15/2012 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
| 06/15/2012 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | IVRS - Inspection :* |
| 07/10/2012 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
| 07/10/2012 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 07/10/2012 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
| 07/10/2012 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
| 07/10/2012 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | IVRS - Inspection :* |
| 07/13/2012 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 07/13/2012 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
| 07/13/2012 | ELECTRIC - PROGRESS | RMORENO | Approved | IVRS - Inspection :* |
| 07/13/2012 | ELECTRIC - TEMP POWER FOR TEST | RMORENO | Approved | IVRS - Inspection :* |
| 07/13/2012 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 07/13/2012 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* |
| 07/19/2012 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 07/19/2012 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
| 07/20/2012 | FIRE - FINAL | WMOTTO | Approved | APPROVED PER STATE FIRE MARSHAL |
| 07/20/2012 | FIRE - KITCHEN EXH HOOD FINAL | WMOTTO | Approved | APPROVED PER STATE FIRE MARSHAL |
| 07/20/2012 | FIRE - ALARM FINAL | WMOTTO | Approved | APPROVED PER STATE FIRE MARSHSAL |
| 07/20/2012 | FIRE SPKLR - FINAL | WMOTTO | Approved | APPROVED PER STATE FIRE MARSHAL |
| 07/20/2012 | NPPO - FINAL | MRUSSO | Approved | |
| 07/20/2012 | SIGN - FINAL | MRUSSO | Approved | |
| 07/24/2012 | MECHANICAL - INTERMEDIATE | JBURGE | Approved | IVRS - Inspection :* |
| 07/24/2012 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 07/25/2012 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 10/11/2012 | CERTIFICATE OF OCCUPANCY | JBURGE | Approved | IVRS - Inspection :* |
| 10/11/2012 | MECHANICAL - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 10/11/2012 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 10/16/2012 | LANDSCAPE - FINAL | MRUSSO | Approved |