Permit: T11CM00868
Permit Details
Apply Date:
03/23/2011
Applicant:
N/A
Description:
5 STORY APT BUILDING - BLDG 1
Contractors:
- CONSTRUCTION ENTERPRISES INC
Permit Reviews
Permit Number - T11CM00868
Permit Status: C of o
Permit Description: 5 STORY APT BUILDING - BLDG 1
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/23/2011 | PLANS OK TO SUBMIT - COMM | 03/23/2011 | COMPLETED |
03/23/2011 | COMMERCIAL - NEW | 04/29/2011 | COMPLETED |
04/29/2011 | RESUBMITTAL - TI ALL | 05/23/2011 | COMPLETED |
05/23/2011 | RESUBMITTAL | 06/23/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11CM00868
Permit Status: C of o
Permit Description: 5 STORY APT BUILDING - BLDG 1
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/23/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T11CM00868
Permit Description: 5 STORY APT BUILDING - BLDG 1
Total Completed Inspections - 40
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/01/2011 | ELECTRIC - UNDERGROUND | LHANLY | Approved | WEST 1/2 OF BLD 1 OK |
08/09/2011 | PLUMBING - PROGRESS | LHANLY | Approved | 30' OF RAIN DRAIN UNDER WEST SLAB OK TO COVER FOR PURPOSES OF MOVING FORWARD ON SLAB-FOUNDATION. DO NOT COVER THE REST OF THIS DRAIN UNTIL IT HAS BEEN SEEN UNDER TEST. |
09/26/2011 | PLUMBING - PRE SLAB | LHANLY | Approved | |
09/26/2011 | PLUMBING - ROUGH, SOIL | LHANLY | Approved | |
09/26/2011 | BUILDING PRE-SLAB | LHANLY | Approved | |
09/26/2011 | STEM WALL/RETAINING WALL | LHANLY | Approved | |
09/26/2011 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | |
10/25/2011 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | |
11/03/2011 | MECHANICAL - PROGRESS | LHANLY | Approved | FIRE DAMPER SUBMITTAL FOR POTTORFF CFD-521 ACCEPTED. |
11/03/2011 | MECHANICAL - ABOVE CEILING | LHANLY | Approved | FIRE DAMPER SUBMITTAL FOR POTTORFF CFD-521 ACCEPTED. |
11/07/2011 | FIRE SPKLR - OH PIPING & HYDRO | CSCHULTZ | Approved | Temporary standpipe to 3rd floor in bldg. 1 approved 200 psi test for 2 hours still need to add more standpipe as bldg. goes up to 5 story. Also psi tested and checked 6" inch pipe to tee that will go to parking level to FDC. Need to install FDC signs on fence by road showing where FDC is at. |
11/07/2011 | FIRE SPKLR - UG, PIPING, HYDRO | CSCHULTZ | Approved | |
11/10/2011 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | IVRS - Inspection :* 1) NEED DWV AND POTABLE BEFORE |
11/30/2011 | ROOF NAILING | LHANLY | Approved | ALL BUT LAST UNIT ON SOUTH 1) PLYWOOD MUST SPAN AT LEAST 3 JOISTS OR BE BLOCKED ON ALL 4 SIDES 2) MISSING STRAPS AT B.U. POST WEST WING, N. SIDE |
11/30/2011 | BUILDING ABOVE CEILING | LHANLY | Approved | |
11/30/2011 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | ALL BUT SOUTH SIDE |
12/07/2011 | BUILDING - PROGRESS | LHANLY | Approved | MET WITH SUPERVISOR "RON" TO TALK ABOUT NEED TO SEE INSIDE OF WALLS WHEN WE DO A STUCCO-MESH INSPECTION. INSULATION MUST BE REMOVED ON FLOORS 1 & 2 FROM AROUND SE CABLES AND PLUMBING. NOT TO INSULATE EXTERIOR WALLS OF 3,4,5 UNTIL LATH HAS BEEN NAILED OFF. |
12/15/2011 | U VALUE FOR WINDOW | LHANLY | Approved | |
12/16/2011 | STUCCO MESH | LHANLY | Approved | EAST WING OK |
12/30/2011 | SHEET ROCK NAILING | DQUINN | Approved | IVRS - Inspection :* |
12/30/2011 | FRAMING | DQUINN | Approved | IVRS - Inspection :* |
12/30/2011 | MECHANICAL - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
12/30/2011 | PLUMBING - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
12/30/2011 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | IVRS - Inspection :* |
02/29/2012 | ELECTRIC - UFER | LHANLY | Approved | |
03/01/2012 | PLUMBING - YARD WTR LINE/TEST | LHANLY | Approved | |
03/01/2012 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
03/01/2012 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
03/05/2012 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED FOR BLDG 1-PANEL 1-18, UNITS #1208,1209,1210,1211,1212,1308,1309,1310,1311,1312,1408,1409,1410,1411,1508,1509,1510 & 1511 PER L. HANLY |
04/05/2012 | PLUMBING - ROOF DRAINS | LHANLY | Approved | |
04/05/2012 | ELECTRIC - TEMP POWER FOR TEST | LHANLY | Approved | |
05/18/2012 | TEP CLEARANCE - PM | JWEATHER | Approved | ECO CLEARED FOR Pnl # 5 - Units 2103, 2203, 2303, 2403, 2503, 2101, 2201 Pnl # 6 - Units 2102, 2202, 2302, 2402, 2502, 2301, 2401, 2501 Pnl # 7 - Units 2104, 2204, 2304, 2404, 2504, 2105, 2205, 2305, 2405, 2505, 2106, 2206, 2306, 2406, 2506 Pnl # 8 - Units 2108, 2208, 2308, 2408, 2508, 2107, 2207, 2307, 2407, 2507 Pnl # 9 - Units 2109, 2209, 2309, 2409, 2509, 2110, 2210, 2310, 2410, 2510 Pnl #10 - Units 3101, 3201, 3301, 3401, 3501, 3102, 3202, 3302, 3402, 3502, 3104, 3204, 3304, 3404, 3405 Pnl #11 - Units 3103, 3203, 3303, 3403, 3503, 3105, 3205, 3305, 3405, 3505, 3106, 3206, 3306, 3406, 3506 Pnl #12 - Units 3109, 3209, 3309, 3409, 3509, 3108, 3208, 3308, 3408, 3508, 3107, 3207, 3307, 3407, 3507 Pnl #13 - Units 3110, 3210, 3310, 3410, 3510, 3111, 3211, 3311, 3411, 3511, 3112, 3212, 3312, 3412, 3512 Pnl #14 - Units 3113, 3213, 3313, 3413, 3513, 3114, 3214, 3314, 3414,3514, 3115, 3215, 3315, 3415, 3515 Pnl #15 - Units 3116, 3216, 3316, 3416, 3516, 3117, 3217, 3317, 3417, 3517, 3118, 3218, 3318, 3418, 3518 |
06/21/2012 | MECHANICAL - FINAL | LHANLY | Approved | |
06/21/2012 | PLUMBING - FINAL | LHANLY | Approved | |
06/21/2012 | ELECTRIC - FINAL | LHANLY | Approved | |
06/21/2012 | ELECTRIC - PROGRESS | LHANLY | Approved | |
06/21/2012 | BUILDING - FINAL | LHANLY | Approved | |
06/22/2012 | FIRE - FINAL | WMOTTO | Approved | |
06/22/2012 | FIRE - ALARM FINAL | WMOTTO | Approved | |
06/22/2012 | FIRE SPKLR - FINAL | WMOTTO | Approved |