Inspection Status: Partial Approval
Inspection History: PLUMBING - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 04/25/2012 |
PLUMBING - PROGRESS |
|
Partial Approval |
|
| 04/25/2012 |
PLUMBING - PROGRESS |
|
Partial Approval |
|
| 04/25/2012 |
PLUMBING - PROGRESS |
|
Approved |
|
| 01/06/2012 |
PLUMBING - PROGRESS |
|
Partial Approval |
8' SEWER FROM MH 1 TO MH 2 |
| 08/09/2011 |
PLUMBING - PROGRESS |
|
Partial Approval |
30' OF RAIN DRAIN UNDER WEST SLAB OK TO COVER FOR PURPOSES OF MOVING FORWARD ON SLAB-FOUNDATION. DO NOT COVER THE REST OF THIS DRAIN UNTIL IT HAS BEEN SEEN UNDER TEST. |
| 07/20/2011 |
PLUMBING - PROGRESS |
|
Partial Approval |
MET CONTRACTOR ON SITE FOR PRELIMINARY REVIEW OF WASTE WATER INSTALLATION. MUST BE RESCHEDULED WHEN TEST IS ON LINE. |