Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T11BU01391
Permit Details
Apply Date:
10/20/2011
Applicant:
N/A
Description:
GRADING
Contractors:
- DIVISION II CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T11BU01391
Permit Status: Final
Permit Description: GRADING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/20/2011 | PLANS OK TO SUBMIT - GRADING | 10/20/2011 | COMPLETED |
10/20/2011 | GRADING | 10/26/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T11BU01391
Permit Status: Final
Permit Description: GRADING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/20/2011 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T11BU01391
Permit Description: GRADING
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/21/2011 | GRADING - TIER REV | jgreen | Approved | Grading plan and "Plot" plan is related to Development Plan package D11-0020. DP has rezoning with it and a required wait period. However per the PDSD Director the applicant wants to start grading the site now and PDSD has agreed to let the plan come back in under the R2 use to allow the grading to commence. However the entire site must provide conformance with the DP package. No buildings or foundations should be constructed at this time. |
03/08/2012 | SWPPP CORRECTION NOTICE | RLEDONNE | Approved | |
03/08/2012 | RAINWATER - FINAL | RLEDONNE | Approved | |
03/08/2012 | RAINWATER - INTERMEDIATE | RLEDONNE | Approved | |
03/08/2012 | STORMWATER INSTALL OF CONTROLS | RLEDONNE | Approved | |
03/08/2012 | GRADING - FINAL | RLEDONNE | Approved | |
03/08/2012 | GRADING - INTERMEDIATE | RLEDONNE | Approved | |
03/08/2012 | GRADING - CHECK FOR ACTIVITY | RLEDONNE | Approved | |
03/08/2012 | GRADING - REBAR | RLEDONNE | Approved | |
03/08/2012 | ENGINEERING PRE-CONSTRUCTION | RLEDONNE | Approved |