Permit: T10CM03061
Permit Details
Apply Date:
11/01/2010
Applicant:
N/A
Description:
TI:BAR
Architects:
- EVANS, JON CHRISTOPHE
Contractors:
- BARKER MORRISSEY CONTRACTING INC **C
Permit Reviews
Permit Number - T10CM03061
Permit Status: Final
Permit Description: TI:BAR
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/19/2011 | REVISION - - 1ST | 01/19/2011 | COMPLETED |
01/19/2011 | REVISION - - 2ND | 01/24/2011 | COMPLETED |
11/01/2010 | COMMERCIAL - TI | 12/15/2010 | COMPLETED |
Completed Inspections
Permit Status: Final
Permit Number: T10CM03061
Permit Description: TI:BAR
Total Completed Inspections - 28
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/19/2011 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
01/20/2011 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* |
01/27/2011 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
01/27/2011 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
02/01/2011 | FRAMING | JBURGE | Approved | IVRS - Inspection :* APPROVED BUILT UP WOOD FLOOR NEW BAR SUPPORT FLOR |
02/07/2011 | MECHANICAL - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
02/07/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
02/07/2011 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
02/07/2011 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | |
02/07/2011 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
02/08/2011 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
02/08/2011 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
02/08/2011 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
02/08/2011 | NPPO - FINAL | MRUSSO | Approved | |
02/08/2011 | LANDSCAPE - FINAL | MRUSSO | Approved | |
02/09/2011 | ENGINEERING - FINAL | MRUSSO | Approved | NO SITE WORK WAS DONE DURING THIS PROJECT, THEREFORE THE C OF O FOR ENGINEERING IS APPROVED. HOWEVER THE EXISTING HC PARKING FOR THE BUSINESS DOES NOT MEET ADAAG/ANSI REQUIREMENTS FOR HC PARKING OR ACCESS. |
02/10/2011 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
02/10/2011 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
02/11/2011 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
02/11/2011 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
02/11/2011 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
02/14/2011 | PLUMBING - FINAL | LHANLY | Approved | |
02/14/2011 | ELECTRIC - FINAL | LHANLY | Approved | |
02/14/2011 | ELECTRIC - ABOVE CEILING | LHANLY | Approved | |
02/14/2011 | ELECTRIC - UNDERGROUND | LHANLY | Approved | |
08/30/2011 | FIRE - FINAL | CSCHULTZ | Approved | |
11/07/2011 | HEALTH DEPT - FINAL 724-7908 | pc health | Approved | |
11/07/2011 | BUILDING - FINAL | LHANLY | Approved |