Permit: T10CM01885
Permit Details
Apply Date:
07/09/2010
Applicant:
N/A
Description:
TUSD SCHOOL
Contractors:
- SUNDT CONSTRUCTION
- TUCSON UNIFIED SCHOOL DIST #1 ** APA
Permit Reviews
Permit Number - T10CM01885
Permit Status: C of o
Permit Description: TUSD SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/14/2011 | 3RD PARTY REVIEW - REVISION/OTHER | 03/29/2011 | COMPLETED |
| 03/21/2011 | 3RD PARTY REVIEW - REVISION/OTHER-2ND | 03/21/2011 | COMPLETED |
| 07/14/2010 | 3RD PARTY REVIEW-COMMERCIAL | 08/23/2010 | COMPLETED |
| 08/23/2010 | POST 3RD PARTY REVIEW | 09/13/2010 | COMPLETED |
| 09/13/2010 | POST 3RD PARTY REVIEW | 10/12/2010 | COMPLETED |
| 10/12/2010 | RESUBMITTAL | 10/15/2010 | COMPLETED |
| 11/21/2011 | 3RD PARTY REVIEW - REVISION/OTHER | 11/22/2011 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM01885
Permit Status: C of o
Permit Description: TUSD SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/09/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM01885
Permit Description: TUSD SCHOOL
Total Completed Inspections - 46
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/08/2010 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* 1) OK #4 TO REBAR + 20' IN FOOTING |
| 11/17/2010 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* 1) AS MARKED ON 1/2 SET TERRACON INSPECTED |
| 11/23/2010 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* 1) OK AS MARKED PVC CONDUITS |
| 11/24/2010 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* 1) 4" SDR 35 FROM MANHOLE #3 TO BLDG #2 TEST OK |
| 11/30/2010 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
| 11/30/2010 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* |
| 12/10/2010 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 12/15/2010 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* 1) PROVIDE APPROVED PLANS FOR ALL CHANGES 2) INSTALLED PER RED LINES 3) CLEANOUTS INSTALLED FOR TEST |
| 12/22/2010 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* 1) OK PVC REPAIRS 2) OK BOND WIRES IN SLAB |
| 12/22/2010 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/22/2010 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/22/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 12/28/2010 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* 1) SPECIAL INSPECTED |
| 02/18/2011 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 03/17/2011 | EXT METAL CLIPS/EXT SHEATHING | MHENSON | Approved | IVRS - Inspection :* 1) CLEAR STORY SHEATHING OK |
| 03/29/2011 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
| 04/18/2011 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
| 04/19/2011 | PLUMBING - BACK WATER VALVE | RRICH | Approved | IVRS - Inspection :* |
| 04/22/2011 | STUCCO MESH | MHENSON | Approved | IVRS - Inspection :* |
| 05/10/2011 | FRAMING | JBURGE | Approved | IVRS - Inspection :* 1) SOUTH WING COMPLETE |
| 05/25/2011 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 06/06/2011 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 07/07/2011 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 07/08/2011 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
| 07/12/2011 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* 1) OK GRID LTG |
| 07/12/2011 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 07/13/2011 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
| 07/15/2011 | FIRE SPKLR - OH PIPING & HYDRO | DSIWARSKI | Approved | |
| 07/15/2011 | FIRE - HYDRANTS | DSIWARSKI | Approved | |
| 07/25/2011 | MECHANICAL - HYDRONIC PIPING | MRAMBER | Approved | IVRS - Inspection :* |
| 08/10/2011 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 08/10/2011 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 08/11/2011 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 08/11/2011 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 08/18/2011 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 08/18/2011 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
| 08/18/2011 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 08/18/2011 | SIGN - FINAL | RLEDONNE | Approved | NA TO THIS BUILDING |
| 08/22/2011 | NPPO - FINAL | RLEDONNE | Approved | NPPO NA TO THIS ACTIVITY. |
| 08/23/2011 | FIRE - ALARM FINAL | DSIWARSKI | Approved | |
| 08/23/2011 | FIRE - LANE SIGNS | DSIWARSKI | Approved | |
| 08/23/2011 | FIRE SPKLR - FINAL | DSIWARSKI | Approved | |
| 08/23/2011 | FIRE - FINAL | DSIWARSKI | Approved | |
| 10/14/2011 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* 1) OK WITH OUT ENGINEERING FINAL PER LEERAY HANLY |
| 11/15/2011 | ENGINEERING - FINAL | DROBERTS | Approved | ALL CERTIFICATION LETTERS WILL BE PROVIDED FOR THIS SITE PRIOR OR DURING THE FINAL GRADING INSPECTION. |
| 11/15/2011 | LANDSCAPE - FINAL | DROBERTS | Approved | ALL CERTIFICATION LETTERS WILL BE PROVIDED FOR THIS SITE PRIOR OR DURING THE FINAL GRADING INSPECTION. |