Permit: T10CM00366
Permit Details
Apply Date:
02/16/2010
Applicant:
N/A
Description:
NEW TACO BELL
Contractors:
- HAWORTH CORPORATION , THE
Permit Reviews
Permit Number - T10CM00366
Permit Status: C of o
Permit Description: NEW TACO BELL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/16/2010 | PLANS OK TO SUBMIT - COMM | 02/16/2010 | COMPLETED |
| 03/02/2010 | COMMERCIAL NEW | 03/23/2010 | COMPLETED |
| 04/07/2010 | RESUBMITTAL | 04/23/2010 | COMPLETED |
| 04/23/2010 | RESUBMITTAL | 05/11/2010 | COMPLETED |
| 05/11/2010 | RESUBMITTAL | 07/15/2010 | COMPLETED |
| 08/11/2010 | REVISION - - 1ST | 08/11/2010 | COMPLETED |
| 08/11/2010 | REVISION - - 1ST | 08/18/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T10CM00366
Permit Status: C of o
Permit Description: NEW TACO BELL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/16/2010 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T10CM00366
Permit Description: NEW TACO BELL
Total Completed Inspections - 48
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/02/2010 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* 1) 20' #4 COPPER |
| 08/05/2010 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
| 08/05/2010 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
| 08/09/2010 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* 1. OK UNDERSLAB CONDUITS IN BLD. 2. OK SIGN & COMM. CONDUITS |
| 08/11/2010 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* 1) OK FOR CONCRETE S.T.O.I. |
| 08/11/2010 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 08/20/2010 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
| 08/23/2010 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | 2) OK TO STUCCO MESH |
| 08/23/2010 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO DRY IN |
| 08/26/2010 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 08/26/2010 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
| 08/26/2010 | PLUMBING - ROOF DRAINS | RMYERS | Approved | IVRS - Inspection :* |
| 08/30/2010 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/01/2010 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/02/2010 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/13/2010 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/16/2010 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* 1) RECEIVED LETTER FOR SES 2) INSTALL PLASTIC BUSHINGS IN PANELS CORRECTLY |
| 09/20/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ-SENT TO TEP ON 09/17/10 IN THE AM |
| 09/21/2010 | PLUMBING - INTERMEDIATE | RMYERS | Approved | CLOSET FLANGES OK |
| 09/22/2010 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
| 09/22/2010 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
| 09/24/2010 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* 1) ADD HANGERS AS REQUIRED |
| 09/29/2010 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/29/2010 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 09/29/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 10/01/2010 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* 1) OK TO COVER YARDWATER |
| 10/05/2010 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 10/06/2010 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 10/06/2010 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 10/06/2010 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
| 10/06/2010 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 10/06/2010 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 10/06/2010 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 10/07/2010 | MECHANICAL - HOODS | MRAMBER | Approved | IVRS - Inspection :* 1) DUCT SMOKE DETECTOR TEST OK 2) AIR BALANCE REPORT OK 3) HOOD SMOKE CONTAINMENT TEST OK |
| 10/07/2010 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 10/07/2010 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 10/08/2010 | FIRE - KITCHEN EXH HOOD FINAL | DRamirez | Approved | Approved 10/8/10 |
| 10/08/2010 | FIRE - FINAL | DRamirez | Approved | Approved 10/8/10 |
| 10/08/2010 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 10/08/2010 | NPPO - FINAL | MRUSSO | Approved | |
| 10/08/2010 | LANDSCAPE - FINAL | MRUSSO | Approved | |
| 10/08/2010 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 10/08/2010 | RIGHT OF WAY - FINAL | M.Otero | Approved | |
| 10/12/2010 | CERTIFICATE OF OCCUPANCY | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/12/2010 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/12/2010 | ZONING - FINAL | JFEMLING | Approved | Final plat recorded |
| 10/14/2010 | SIGN - FINAL | LHANLY | Approved | |
| 10/14/2010 | HEALTH DEPT - FINAL 724-7908 | NRAMIREZ | Approved |