| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/03/2010 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 03/03/2010 | RONALD BROWN | ZONING HC | REVIEW | Approved | |
| 03/04/2010 | JASON GREEN | ENGINEERING | REVIEW | Denied | DATE: March 4, 2010 REVIEWERS: Jason Green, CFM ACTIVITY: T10CM00366 (Building Plan) SUMMARY: Engineering Division of Development Services Department has received the building plan (T10CM00366). Engineering Division does not recommend approval of the building plan application at this time. The following items need to be addressed: BUILDING PLAN COMMENTS: 1) Engineering could not verify that the building plan was in compliance with the stamped approved Development Plan (D09-0039). Please submit two copies of the stamped approved Development Plan, landscape, and NPPO plans with the next building plan submittal. 2) Engineering will re-review the building plan on the next submittal to insure compliance with the approved and stamped Development Plan. Additional comments may be forthcoming. GENERAL COMMENTS: Please provide the building plan with a copy of the last approved Development Plan (D09-0039). Further comments may be generated upon resubmittal of the building plan review. For questions or to schedule an appointment I can be reached at 837-4929. Jason Green, CFM Senior Engineer Associate Engineering Division COT Development Services |
| 03/04/2010 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. Need to provide special inspection certifications. 2. Need to provide a letter to LeeRay Hanly for a summary of deferred submittals. 3. Show structural details and calculations for support of exhaust hood. END OF REVIEW |
| 03/10/2010 | STEVE SHIELDS | ZONING | REVIEW | Denied | PDSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Taco Bell @ 1720 W. Speedway BL. T10CM00366 Building Plan (1st Review) TRANSMITTAL DATE: March 10, 2010 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. The building plans appear to be in compliance with the last submitted Development package. At this time the Development package has not been approved by all PDSD agencies therefore zoning cannot approve the building plans. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped Development Package. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\grading\t10cm00366.doc |
| 03/11/2010 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 03/19/2010 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Coordinate the civil utility drawings with the plumbing plans. The Private Grading and Utility Plan (sheet 1 of 2) calls out a 2" meter and RPBP along with a 1-1/4" water service line to the building. Reference: Section 103.2.3, UPC 2006. 2. Clarify the gas input to the water heater (WH-1); it is scheduled as 120 MBH input on sheet P1.0 and 199.9 MBH on sheet P5.0. Reference: Section 103.2.3, UPC 2006. 3. Provide detail 20/A6.0 referenced on detail 2/P6.0 and clarify the illegible clearance dimensions for the termination of the direct vent and the combustion air inlet. 4. Hub drains (key notes 2 and 4, P2.0, key note 9, P5.0, and key note 5, detail 2/P6.0) are not approved for use under the UPC; they do not comply with Sections 411.1 and 804.1, UPC 2006. 5. The branch piping size called out for the urinal flush valve will result in a water velocity greater than 8 FPS. Limit the water velocity to less than 8 FPS for the copper piping. Reference: Section A 6.1, UPC 2006 and Section 2.6, IS 3-2003. 6. Include the water demand (e.g. ice makers, beverage dispensers, etc.) from the filtered water system with the water calculations. (Note that the restaurant is an assembly occupancy when determining the fixture units for the water closets and the urinal.) Reference: Section 610.1, UPC 2006. 7. Appliances (e.g. coffee makers, ice makers, etc) to be directly connected to the water supply system that do not have listed, integral backflow preventers or have integral air gaps conforming to Table 6-3, UPC 2006 require backflow prevention. Indicate how backflow protection will be provided for each appliance. Reference: Sections 602.3, 603.0, and Table 6-2, UPC 2006. 8. Provide a direct waste connection for the wash and rinse sections of the 3-compartment sink, with an indirect connection for the sanitizing compartment only. Reference: Sections 304.0 and 801.2.3, UPC 2006. 9. Provide a protecting vent for each fixture (e.g. floor drains). Reference: Section 901.0, UPC 2006. 10. Clarify the need for a vented flow control device for a gravity grease interceptor. Unless the manufacturer of the interceptor requires one, a flow control device in this application would be an obstruction to flow. Reference: Sections 311.5 and 1014.3.3.1, UPC 2006. |
| 03/19/2010 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide energy code compliance calculations for the building envelope (the correct climate zone is Pima County < 4,000 feet). Reference: Section 101.4, International Energy Conservation Code 2006. 2. Specify the minimum resistance (R-value) of the duct insulation to be used on this project. Reference: Section 503.2.7, IECC 2006, as amended by the City of Tucson. 3. Provide calculations demonstrating adequate ventilation. Reference: Section 401.2, IMC 2006. 4. Provide information to show that the exhaust fan for the Type I hood starts automatically when cooking operations commence. Reference: Section 507.2.1.1, IMC 2006. 5. Provide structural calculations and details to show that the Type I hood is supported from the building structure (i.e. how do the all-thread rods attach to the building structure) in accordance with Section 507.6, IMC 2006. Reference: Section 302.1, IMC 2006. 6. Show that the roof top air-conditioning units supplying make up air for the kitchen hood are electrically interlocked to the exhaust fans. Reference: Section 508.1, IMC 2006. |
| 03/19/2010 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 03/22/2010 | GERRY KOZIOL | WWM | REVIEW | Denied | TACO BELL- ISSUED WITH GREASE INTERCEPTOR 3- CPT SINK & PREP SINK INDIRECT TO FS'S NEED PCRWRD 3RD FLOOR REVIEW OF LOCATION/METHOD OF CONNECTION TO PUBLIC SEWER THROUGH PRIVATE SEWER ON ADJACENT PARCEL- CHAD 740-6547 |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 03/23/2010 | CPIERCE1 | OUT TO CUSTOMER | Completed |