Permit: T09CM03201
Permit Details
Status:
Final
Type:
COMMERCIAL ALTERATION
Address:
3619 E SPEEDWAY BL #103
Address NEW:
3619 E SPEEDWAY BL #103
Apply Date:
12/07/2009
Applicant:
N/A
Description:
TI: WAREHOUSE
Contractors:
- BARKER MORRISSEY CONTRACTING INC **C
Permit Reviews
Permit Number - T09CM03201
Permit Status: Final
Permit Description: TI: WAREHOUSE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/07/2009 | COMMERCIAL TI | 12/10/2009 | COMPLETED |
| 12/10/2009 | COMMERCIAL TI | 12/14/2009 | COMPLETED |
| 12/14/2009 | RESUBMITTAL | 01/13/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM03201
Permit Status: Final
Permit Description: TI: WAREHOUSE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/07/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM03201
Permit Description: TI: WAREHOUSE
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/01/2010 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* AS BUILT ON SITE OK TO COVER |
| 02/05/2010 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* 1) OK FOR CONCRETE |
| 02/24/2010 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* CAN LITES IN HARD CEILINGS OK |
| 02/24/2010 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
| 02/24/2010 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 03/02/2010 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/23/2010 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* 1) FLANGES OK 2) OVERHEAD INSULATION ALREADY STARTING TO COME APART |
| 03/30/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* 1) STILL NEED TO SEE LINE SET FOR MINI SPLIT |
| 04/08/2010 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
| 04/08/2010 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
| 04/08/2010 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
| 04/09/2010 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
| 04/12/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 04/12/2010 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 04/12/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 04/12/2010 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1) CLOSET FLANGES OK |
| 08/06/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 08/06/2010 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 08/06/2010 | FIRE - FINAL | LTHOMAS | Approved | |
| 08/06/2010 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
| 08/06/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 08/06/2010 | ELECTRIC - PROGRESS | RJIROUDE | Approved | IVRS - Inspection :* |
| 08/09/2010 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |