Permit: T09CM03199
Permit Details
Apply Date:
12/07/2009
Applicant:
N/A
Description:
TI: RETAIL SHOWROOM
Architects:
- BREMS, DAVID PAUL
Contractors:
- LAYTON INTERIOR SPECIALISTS OF ARIZONA
Permit Reviews
Permit Number - T09CM03199
Permit Status: Final
Permit Description: TI: RETAIL SHOWROOM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/25/2010 | COMMERCIAL TI | 01/26/2010 | COMPLETED |
01/26/2010 | COMMERCIAL TI | 01/27/2010 | COMPLETED |
02/12/2010 | REVISION - - 1ST | 02/12/2010 | COMPLETED |
12/07/2009 | COMMERCIAL TI | 01/25/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM03199
Permit Status: Final
Permit Description: TI: RETAIL SHOWROOM
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/07/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM03199
Permit Description: TI: RETAIL SHOWROOM
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/28/2010 | ELECTRIC - CONSTRUCTION POWER | RJIROUDE | Approved | IVRS - Inspection :* |
01/29/2010 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
01/29/2010 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
02/02/2010 | FRAMING | GDABBS | Approved | IVRS - Inspection :* FRAMING APPROVED |
02/04/2010 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) DWV THRU ROOF OK 2) WATER DISTRIBUTION OK 3) CLOSET FLANGE OK FOR VINAL COMPOSITE TILE |
02/04/2010 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
02/16/2010 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
02/17/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER R. MORENO |
02/19/2010 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* 1) TEST FROM METER LOCATION THRU TO (3) ROOF TOP UNITS THRU VALVES AND FLEXES 2) OK FOR GAS CLEARANCE FROM MECH INSP. |
02/19/2010 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
02/22/2010 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
02/22/2010 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :*NO SIGN ON SITE |
02/22/2010 | ENGINEERING - FINAL | DROBERTS | Approved | |
02/22/2010 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
02/23/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* 1) STEP UP CONDENSATE TO 1" AT 1ST TEE 2) INSULATE RETURN AIR TEE 3) LEFT GAS CARD 4) PROVIDE ACCESS TO FIRE DAMPERS AND INSTALL FIRE DAMPERS PER INSTRUCTIONS |
02/23/2010 | NPPO - FINAL | ACONNOR | Approved | N/A |
02/23/2010 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
02/25/2010 | FIRE - FINAL | CSCHULTZ | Approved | C of O FOR SHELL ONLY |
03/03/2010 | PLUMBING - PROGRESS | RRICH | Approved | |
03/03/2010 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
03/08/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
03/08/2010 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved | |
03/08/2010 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | |
03/08/2010 | ELECTRIC - UFER | RJIROUDE | Approved | |
03/08/2010 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
03/08/2010 | ELECTRIC - PROGRESS | RJIROUDE | Approved | IVRS - Inspection :* |
03/08/2010 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
03/08/2010 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
03/16/2010 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
03/16/2010 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
03/17/2010 | PERMIT FINALED | JWEATHER | Approved |