Permit: T09CM02912
Permit Details
Apply Date:
11/03/2009
Applicant:
N/A
Description:
TI: RESTAURANT
Contractors:
- CAYLOR CONSTRUCTION COMPANY , RO
Permit Reviews
Permit Number - T09CM02912
Permit Status: C of o
Permit Description: TI: RESTAURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/06/2010 | RESUBMITTAL | 01/07/2010 | COMPLETED |
| 01/27/2010 | REVISION - - 1ST | 01/27/2010 | COMPLETED |
| 11/03/2009 | COMMERCIAL TI | 11/03/2009 | COMPLETED |
| 11/03/2009 | COMMERCIAL TI | 12/04/2009 | COMPLETED |
| 12/16/2009 | RESUBMITTAL | 01/06/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02912
Permit Status: C of o
Permit Description: TI: RESTAURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/03/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM02912
Permit Description: TI: RESTAURANT
Total Completed Inspections - 39
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/08/2010 | PLUMBING - ROUGH, SOIL | MYERS | Approved | DWV UNDER SLAB OK TO COVER WATER TEST COMPLETE NEED TO SEE FINAL VENT CORRECTIONS |
| 01/08/2010 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 01/08/2010 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 01/11/2010 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* 1) OK TO COVER UNDERSLAB |
| 01/12/2010 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/20/2010 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection :* |
| 01/26/2010 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* 1) INSTALL PER PLAN OR AT LEAST RED LINE CHANGES OR DELETIONS 2) GAS FOR KITCHEN LINE, ANSUL VALVE, AND CONNECTION TO EXISTING OK 3) PRESSURE TEST OK |
| 01/27/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
| 01/28/2010 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* 1) OK TO COVER |
| 02/17/2010 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/04/2010 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
| 03/04/2010 | MECHANICAL - HOODS | JMILITEL | Approved | IVRS - Inspection :* |
| 03/04/2010 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* 1) MAKE UP AIR ISSUE HAS BEEN RESOLVED |
| 03/04/2010 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 03/04/2010 | FIRE SPKLR - FINAL | DRamirez | Approved | Approved 3/4/10 |
| 03/04/2010 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
| 03/05/2010 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
| 03/09/2010 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/09/2010 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/09/2010 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/09/2010 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* |
| 03/09/2010 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 03/09/2010 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
| 03/09/2010 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 03/09/2010 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 03/10/2010 | ELECTRIC - PROGRESS | DSANTACR | Approved | |
| 03/10/2010 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | |
| 03/10/2010 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
| 03/10/2010 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 03/10/2010 | NPPO - FINAL | ACONNOR | Approved | N/A |
| 03/10/2010 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
| 03/10/2010 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 03/11/2010 | FIRE - KITCHEN EXH HOOD FINAL | DRamirez | Approved | Approved 3/11/10 |
| 03/11/2010 | FIRE - FINAL | DRamirez | Approved | Approved 3/11/10 |
| 03/11/2010 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 03/12/2010 | BUILDING - FINAL | AQUIROZ | Approved | |
| 03/12/2010 | SIGN - FINAL | JYBARRA | Approved | |
| 03/12/2010 | FIRE - ALARM FINAL | DSIWARSKI | Approved | |
| 03/12/2010 | HEALTH DEPT - FINAL 724-7908 | NRAMIREZ | Approved |