Permit: T09CM02126
Permit Details
Apply Date:
08/07/2009
Applicant:
N/A
Description:
NEW RESTAURANT
Architects:
- EDWARDS, PATRICK DEAN
Contractors:
- M C O AND ASSOCIATES L L C
Permit Reviews
Permit Number - T09CM02126
Permit Status: C of o
Permit Description: NEW RESTAURANT
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/17/2010 | REVISION - - 1ST | 02/26/2010 | COMPLETED |
| 02/26/2010 | REVISION - - 2ND | 03/05/2010 | COMPLETED |
| 08/07/2009 | PLANS OK TO SUBMIT - COMM | 08/07/2009 | COMPLETED |
| 08/10/2009 | COMMERCIAL NEW | 09/21/2009 | COMPLETED |
| 11/10/2009 | RESUBMITTAL | 12/10/2009 | COMPLETED |
| 12/10/2009 | RESUBMITTAL | 12/17/2009 | COMPLETED |
| 12/17/2009 | RESUBMITTAL | 01/19/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM02126
Permit Status: C of o
Permit Description: NEW RESTAURANT
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/07/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM02126
Permit Description: NEW RESTAURANT
Total Completed Inspections - 44
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/22/2010 | ROOF NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 03/03/2010 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 03/05/2010 | FRAMING | MHENSON | Approved | IVRS - Inspection :* APPROVED |
| 03/05/2010 | EXT METAL CLIPS/EXT SHEATHING | MHENSON | Approved | IVRS - Inspection :* EXT CLIP & LATHING APPROVED INTERIOS SH--- OK NORTH WALL |
| 03/11/2010 | EXCAVATION/LAYOUT REBAR & ZON | MHENSON | Approved | IVRS - Inspection :* |
| 03/15/2010 | STUCCO MESH | GDABBS | Approved | IVRS - Inspection :* |
| 03/17/2010 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 03/18/2010 | REINFORCED MASONRY PRE-GROUT | MHENSON | Approved | IVRS - Inspection :* |
| 03/26/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* 1) DUCT ABOVE CEILING OK 2) FLUE PIPING FOR WATER HEATER NOT INSTALLED, DO NOT COVER |
| 03/29/2010 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 03/29/2010 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
| 03/29/2010 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 03/29/2010 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
| 03/30/2010 | NPPO - FINAL | JLINVILLE | Approved | n/a |
| 03/30/2010 | TEP CLEARANCE - AM | JWEATHER | Approved | TMPP CLEARED PER R. HOLLANDER |
| 04/06/2010 | MECHANICAL - HOODS | MRAMBER | Approved | IVRS - Inspection :* 1) AIR BALANCE REPORT OK 2) DUCT SMOKE DETECTOR TEST OK X 3 3) INTERLOCK BETWEEN MUS & EXH ON KITCHEN HOOKS OK X 2 4) HEST SENSOR INTERLOCK OK X 2 5) SMOKE CONTAINMENT TEST ON HOODS OK X 2 6) COAT ARMOR FLEX ON ROOF WITH PROCECTIVE COATING PER MOVE INSTALLATION INSTRUCTIONS 7) PROVIDE SCREENS IN W/H FLUE AND INTAKE TERMINATIONS 8) DUCT TAPE NOT ALLOWED ON ARMORFLEX EXPOSED TO EXTERIOR 9) AC-3 FLUE EXHAUST TOO CLOSE TO AC-2 INTAKE (O.S.A.) |
| 04/06/2010 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/06/2010 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/07/2010 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
| 04/08/2010 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* 1) RECEIVED LETTER OF TORQUE |
| 04/08/2010 | PLUMBING - PROGRESS | RLEDONNE | Approved | |
| 04/08/2010 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | |
| 04/08/2010 | PLUMBING - PRE SLAB | RLEDONNE | Approved | |
| 04/08/2010 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/08/2010 | PLUMBING - ROOF DRAINS | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/08/2010 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 04/08/2010 | ELECTRIC - PROGRESS | DSANTACR | Approved | IVRS - Inspection :* |
| 04/08/2010 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 04/08/2010 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 04/08/2010 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
| 04/08/2010 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 04/08/2010 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 04/08/2010 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 04/08/2010 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
| 04/08/2010 | FIRE - KITCHEN EXH HOOD FINAL | DRamirez | Approved | Approved 4/7/10 |
| 04/08/2010 | FIRE - FINAL | DRamirez | Approved | Approved 4/7/10 |
| 04/09/2010 | HEALTH DEPT - FINAL 724-7908 | NRAMIREZ | Approved | |
| 04/09/2010 | MECHANICAL - FINAL | LHANLY | Approved | |
| 04/09/2010 | ELECTRIC - TEMP POWER FOR TEST | LHANLY | Approved | |
| 04/09/2010 | BUILDING - FINAL | LHANLY | Approved | |
| 04/09/2010 | SIGN - FINAL | LHANLY | Approved | |
| 04/14/2010 | RIGHT OF WAY - FINAL | LLopez | Approved | |
| 04/16/2010 | ENGINEERING - FINAL | BGRANT | Approved | HOLD GRADING BOND TILL GRADING PERMIT FINALED FOR SITE |
| 04/16/2010 | LANDSCAPE - FINAL | ACONNOR | Approved |