Permit: T09CM00182
Permit Details
Apply Date:
01/23/2009
Applicant:
N/A
Description:
ADDITION: "FINISH PRODUCT" STORAGE
Contractors:
- STELLAR CORPORATION ,
Permit Reviews
Permit Number - T09CM00182
Permit Status: Final
Permit Description: ADDITION: "FINISH PRODUCT" STORAGE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/23/2009 | PLANS OK TO SUBMIT - COMM | 01/26/2009 | COMPLETED |
01/26/2009 | COMMERCIAL NEW | 03/05/2009 | COMPLETED |
03/05/2009 | RESUBMITTAL | 04/03/2009 | COMPLETED |
04/03/2009 | RESUBMITTAL | 04/21/2009 | COMPLETED |
04/21/2009 | RESUBMITTAL | 05/11/2009 | COMPLETED |
05/11/2009 | OTHER | 05/12/2009 | COMPLETED |
05/20/2009 | REVISION - - 1ST | 05/22/2009 | COMPLETED |
05/22/2009 | RESUBMITTAL | 06/01/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM00182
Permit Status: Final
Permit Description: ADDITION: "FINISH PRODUCT" STORAGE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/23/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09CM00182
Permit Description: ADDITION: "FINISH PRODUCT" STORAGE
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/25/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
08/11/2009 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
08/11/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
08/12/2009 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
08/12/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
08/12/2009 | PLUMBING - ROOF DRAINS | RRICH | Approved | IVRS - Inspection :* |
08/12/2009 | NPPO - FINAL | ACONNOR | Approved | |
08/12/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
08/18/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL |
08/18/2009 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
08/18/2009 | FIRE - FINAL | CSCHULTZ | Approved | |
08/18/2009 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
08/18/2009 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
08/18/2009 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
08/18/2009 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* |
08/18/2009 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* |
08/18/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
08/18/2009 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
08/18/2009 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
08/18/2009 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
08/18/2009 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
08/18/2009 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* |
08/18/2009 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
08/20/2009 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
08/20/2009 | ENGINEERING - FINAL | DROBERTS | Approved | I MET WITH THE DEVELOPER AND DISCUSSED THE REMAINING WORK THAT IS STILL NEEDED ON HIS SITE, AND WHAT IT WILL TAKE TO GET IT ALL COMPLETE. THE PREVIOUSLY NOTED ROCK RIP RAP HAS BEEN COMPLETED AS WELL AS THE MINOR GRADING OF THE SLOPES. THE CONTRACTOR HAS NOT ESTABLISHED THE TYPE OF MATERIAL THAT WILL BE NEED TO STABALIZE ALL OF THE OPEN AREAS, BUT HAS DISCUSSED IT WITH JOSEPH LINVILLE OF THE ZONING SECTION, THIS WORK WILL START TOMORROW MORNING. IF THE WORK IS NOT FULLY COMPLETED WITHIN A TIMELY MANOR A NOTICE OF VIOLATION WILL BE ISSUED TO THE PROPERTY OWNER FOR NOT FULLY DEVELOPING THE PROPERTY PER THE APPROVED STANDS AND SPECIFICATIONS OF THIS DEPARTMENT. |