Permit Reviews
Permit Number - T09CM00065
Permit Status: C of o
Permit Description: 4 PLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/09/2009 | PLANS OK TO SUBMIT - COMM | 01/09/2009 | COMPLETED |
| 01/09/2009 | PLANS OK TO SUBMIT - SITE | 01/09/2009 | COMPLETED |
| 01/09/2009 | COMMERCIAL NEW | 02/02/2009 | COMPLETED |
| 01/09/2009 | SITE | 02/02/2009 | COMPLETED |
| 02/23/2009 | RESUBMITTAL - SITE ALL | 03/04/2009 | COMPLETED |
| 02/23/2009 | RESUBMITTAL | 03/04/2009 | COMPLETED |
| 03/04/2009 | RESUBMITTAL - SITE | 03/10/2009 | COMPLETED |
| 03/04/2009 | RESUBMITTAL | 03/10/2009 | COMPLETED |
| 03/26/2009 | REVISION - - 1ST | 04/01/2009 | COMPLETED |
| 03/30/2009 | REVISION - SITE | 04/03/2009 | COMPLETED |
| 05/14/2009 | REVISION - - 2ND | 05/14/2009 | COMPLETED |
| 05/28/2009 | REVISION - - 2ND | 06/10/2009 | COMPLETED |
| 06/24/2009 | REVISION - - 3RD | 06/30/2009 | COMPLETED |
| 06/24/2009 | REVISION - - 4TH | 06/24/2009 | COMPLETED |
| 07/29/2009 | REVISION - SITE | 10/09/2009 | COMPLETED |
| 10/09/2009 | REVISION - SITE | 10/09/2009 | COMPLETED |
| 12/28/2009 | REVISION - SITE | 01/07/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09CM00065
Permit Status: C of o
Permit Description: 4 PLEX
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/09/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T09CM00065
Permit Description: 4 PLEX
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/24/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* PLEASE POST YOUR ADDRESS! OK TO COVER UNDERGROUND OK TO COVER SEWER |
| 03/24/2009 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
| 03/27/2009 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* OK FOR CONCRETE S.T.O.I |
| 03/27/2009 | BUILDING PRE-SLAB | JBURGE | Approved | OK TO POUR SLAB |
| 03/27/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :$ OK TO POUR CONTINUOUS FOOTINGS |
| 04/16/2009 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* (TRUSS CALCULATIONS PRESENT) OK TO DRY IN |
| 04/17/2009 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | CLIPS AND STRAPS ARE IN PLACE PER PLANS SHEATHING COMPLETE OK TO STUCCO MESH |
| 05/07/2009 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
| 05/14/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* OK FOR SHEETROCK |
| 05/18/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* WALL AND CEILING ALL OK |
| 05/18/2009 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* |
| 05/21/2009 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* TRUSS SYSTEM |
| 05/21/2009 | FRAMING | JBURGE | Approved | IVRS - Inspection :* OK TO SHEETROCK THROUGHOUT |
| 06/01/2009 | FIREWALL/FIREBARRIER/FIRESTOP | JBURGE | Approved | IVRS - Inspection :* FIRE WALLS CAULKED |
| 06/01/2009 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* OK TO STUCCO EXTERIOR |
| 06/05/2009 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO TAPE THROUGHOUT (UNITS A & B) |
| 07/06/2009 | ELECTRIC - SERVICE UPGRADE | RMORENO | Approved | IVRS - Inspection :* 1) SERVICE AND SUB PANEL-OK 2) FRONT PATIO WALL 2-3/R PVC OK |
| 07/06/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED FOR #1101, 1102, 1103 & 1104 PER R. MORENO |
| 07/24/2009 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* 1) CLOSET FLANGES-OK |
| 07/24/2009 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 07/27/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | Wall was built in front of required landscape buffer; Wall was not reviewed and/or approved by landscape. |
| 07/27/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 07/27/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 07/29/2009 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 07/29/2009 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
| 07/29/2009 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | IVRS - Inspection :* |
| 07/29/2009 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* |
| 07/29/2009 | ELECTRIC - UFER | RMORENO | Approved | IVRS - Inspection :* |
| 07/30/2009 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* ALL TRADES & FIRE FINALS ARE COMPLETE |
| 07/30/2009 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* |
| 07/30/2009 | PLUMBING - FINAL | RMYERS | Approved | |
| 07/30/2009 | PLUMBING - PROGRESS | RMYERS | Approved | |
| 08/06/2009 | ELECTRIC - TEMP POWER FOR TEST | LHANLY | Approved | |
| 08/06/2009 | U VALUE FOR WINDOW | LHANLY | Approved | |
| 08/06/2009 | ELECTRIC - CABLE DROP | LHANLY | Approved | |
| 09/28/2010 | ENGINEERING - FINAL | DROBERTS | Approved |