Permit: T09BU01907
Permit Details
Apply Date:
12/29/2009
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
GRADING: Taco Bell- revision to site.
Contractors:
- CRAFT CONSTRUCTION COMPANY
Permit Reviews
Permit Number - T09BU01907
Permit Status: Final
Permit Description: GRADING: Taco Bell- revision to site.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/10/2010 | RESUBMITTAL - GRADING ALL | 04/07/2010 | COMPLETED |
04/15/2010 | RESUBMITTAL - GRADING ALL | 04/23/2010 | COMPLETED |
04/23/2010 | RESUBMITTAL - GRADING | 05/13/2010 | COMPLETED |
05/13/2010 | RESUBMITTAL - GRADING | 06/11/2010 | COMPLETED |
06/11/2010 | RESUBMITTAL - GRADING | 07/26/2010 | COMPLETED |
07/26/2010 | REVISION - GRADING | 08/04/2010 | COMPLETED |
12/29/2009 | PLANS OK TO SUBMIT - GRADING | 12/29/2009 | COMPLETED |
12/29/2009 | GRADING | 02/05/2010 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T09BU01907
Permit Status: Final
Permit Description: GRADING: Taco Bell- revision to site.
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
12/29/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09BU01907
Permit Description: GRADING: Taco Bell- revision to site.
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/23/2010 | ENGINEERING PRE-CONSTRUCTION | DROBERTS | Approved | CONTRACTOR HAS STARTED WORK ON THIS SITE, REMINDED THEM THAT THEY DID NOT SCHEDULE THEIR PRE CONSTRUCTION MEETING. NO CONCERNS AT THIS TIME DUE TO THE SITE BEING WITHIN A PAVED PARKING LOT AREA. |
09/22/2010 | LANDSCAPE INSPECTION | DROBERTS | Approved | |
09/22/2010 | GRADING - FINAL | DROBERTS | Approved | CREWS HAVE COMPLETED MOST OF THE WORK ON THIS SITE BUT STILL NEED THE FOLLOWING 2 ITEMS: 1) THE HANDICAP SIGNS FOR THE NORTH PARKING SPACES NEED TO BE INSTALLED ONTO POLES PER OUR APPROVED STANDARDS. 2) INSTALL THE TRUNCATED DOMES FOR THE CROSS-WALK IN THIS SAME AREA AS SHOWN ON THE APPROVED PLANS. |
09/22/2010 | GRADING - INTERMEDIATE | DROBERTS | Approved | |
09/22/2010 | GRADING - CHECK FOR ACTIVITY | DROBERTS | Approved | |
09/22/2010 | GRADING - REBAR | DROBERTS | Approved | |
09/22/2010 | GRADING - TIER REV | DROBERTS | Approved |