Permit: T09BU01848
Permit Details
Apply Date:
12/16/2009
Applicant:
BRIAN STIMATZE
Description:
GRADING:
Contractors:
- K G M ENTERPRISES L L C
Outstanding Activity Conditions
Permit Number - T09BU01848
Permit Status: Final
Permit Description: GRADING:
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/16/2009 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T09BU01848
Permit Description: GRADING:
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/11/2010 | ENGINEERING PRE-CONSTRUCTION | JFEMLING | Approved | Met Contractor on site KGM Enterprises, (623-516-1071), discussed grading plans and SWPPP. He plans on grading parking lot next week and paving by the end of the week. He will install controls if paving is not complete next week. Will check on NOI did not have a copy at the job site. Will install conc. washout when begin building. |
| 12/16/2010 | STORMWATER INSTALL OF CONTROLS | JFEMLING | Approved | Project on hold, no storm concerns at this time. |
| 12/16/2010 | GRADING - INTERMEDIATE | JFEMLING | Approved | Project is on hold, parking lot is paved but not LS |
| 06/22/2011 | GRADING - TIER REV | ELEIBOL1 | Approved | New sidewalk along south side of new bldg is constructed flush with parking area. Adjacent stalls will have wheel stops. All 4 roof drains will need to drain across sidewalk since there is no vertical clearance to install scuppers. As-builts to-be-submitted will show all site changes (including this south sidewalk and revised accessibility route and as-built elevations). |
| 12/08/2011 | GRADING - CHECK FOR ACTIVITY | RDELONNE | Approved | |
| 12/08/2011 | GRADING - REBAR | RLEDONNE | Approved | |
| 12/08/2011 | LANDSCAPE INSPECTION | RLEDONNE | Approved | |
| 12/09/2011 | GRADING - FINAL | RLEDONNE | Approved | APPROVED WITH E-MAIL 12-7-2011 FROM JIM VOGELSBERG AND GRADING CERT LETTER FROM ARCHITECT. |
| 03/01/2012 | PERMIT FINALED | KMEDINA | Approved |