Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 12/08/2011 |
GRADING - INTERMEDIATE |
|
Approved |
|
| 12/08/2011 |
GRADING - INTERMEDIATE |
|
Approved |
|
| 11/18/2011 |
GRADING - INTERMEDIATE |
|
Continued |
DROPED OFF PEDESTRIAN ACCESS STANDARD HAND OUT FOR ROOF DRAINS THAT GO OVER THE SIDE WALK ON THE SOUTH SIDE OF THE BUILDING. |
| 11/09/2011 |
GRADING - INTERMEDIATE |
|
Continued |
PROVIDE LETTER FROM PDSD ENGINEERING. |
| 10/25/2011 |
GRADING - INTERMEDIATE |
|
Continued |
MET WITH DAVE AT JOB SITE TO LOOK AT ROOF DRAINS. |
| 10/21/2011 |
GRADING - INTERMEDIATE |
|
Continued |
NO AP PLANS ON SITE. |
| 08/30/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Met with new contractor and discussed plans and what was needed to finish project. |
| 08/25/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Noticed that down spouts from roof are dropping directly onto the sidewalk and access ramp. Called contractor and he said he has a letter from PDSD engineering that approves this method. |
| 08/11/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Work continues on building, some sidewalk has been completed |
| 07/27/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Work has begun again on parking lot and sidewalk around the building. No problems at this time. |
| 04/27/2011 |
GRADING - INTERMEDIATE |
|
Continued |
Slow progress on the building, no site work outside of building. |
| 02/01/2011 |
GRADING - INTERMEDIATE |
|
Continued |
No grading activity at this time, minor bldg activity., very slow progress. |
| 12/16/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Project is on hold, parking lot is paved but not LS |
| 08/10/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Work has stopped at this site no contractor on site, site is secure. |
| 04/06/2010 |
GRADING - INTERMEDIATE |
|
Partial Approval |
Parking lot is paved and stripped, need to install curbs at planters |
| 03/17/2010 |
GRADING - INTERMEDIATE |
|
Continued |
Contractor working on site walls and sidewalk along Palo Verde St. |