Permit Reviews

Permit Number - T09BU00928
Permit Status: Final
Permit Description: GRADING: TPD Crime Lab building and associated Vehicular Use Area.
Start Date Submittal Complete Date Status  
03/22/2010 REVISION - GRADING 03/24/2010 COMPLETED Review Details
06/25/2009 PLANS OK TO SUBMIT - GRADING 06/25/2009 COMPLETED Review Details
06/25/2009 GRADING 07/23/2009 COMPLETED Review Details
10/09/2009 RESUBMITTAL - GRADING ALL 11/03/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T09BU00928
Permit Status: Final
Permit Description: GRADING: TPD Crime Lab building and associated Vehicular Use Area.
Total Outstanding Activity Conditions - 1
Date Name
06/25/2009 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T09BU00928
Permit Description: GRADING: TPD Crime Lab building and associated Vehicular Use Area.
Total Completed Inspections - 10
Date Description Inspector Results Comments
12/02/2009 STORMWATER INSTALL OF CONTROLS MRUSSO Approved 1) TEMP SEDIMENT CONTROLS HAVE BEEN INSTALLED PER PLAN - SUPPLEMENTAL CONTROLS MAY BE NEEDED BASED UPON HOW CURRENT CONTROLS PERFORM.
2) ENSURE YOU PERFORM REQ STORM WATER SELF INSPECTIONS PER YOUR PLAN.
3) ROUTINELY SWEEP UP TRACKED MATERIALS OFF SURROUNDING PUBLIC ROADWAYS.
4) INSTALL AND MAINTAIN A CONCRETE/MATERIALS WASH-OUT PER PLAN.
5) CALL FOR INSPECTION FOR ANY PROSOSED GRADING CHANGES, CONCERNS, AND/OR QUESTIONS.
12/02/2009 ENGINEERING PRE-CONSTRUCTION MRUSSO Approved 1) TEMP SEDIMENT CONTROLS HAVE BEEN INSTALLED PER PLAN - SUPPLEMENTAL CONTROLS MAY BE NEEDED BASED UPON HOW CURRENT CONTROLS PERFORM.
2) ENSURE YOU PERFORM REQ STORM WATER SELF INSPECTIONS PER YOUR PLAN.
3) ROUTINELY SWEEP UP TRACKED MATERIALS OFF SURROUNDING PUBLIC ROADWAYS.
4) INSTALL AND MAINTAIN A CONCRETE/MATERIALS WASH-OUT PER PLAN.
5) CALL FOR INSPECTION FOR ANY PROSOSED GRADING CHANGES, CONCERNS, AND/OR QUESTIONS.
12/08/2010 GRADING - INTERMEDIATE MRUSSO Approved 1) SITE IS UNDER A STORM WATER PERMIT AND MUST COMPLY WITH THE APPROVED STORM WATER PLAN UNTIL THE SITE IS 100% PAVED.
2) RE-ESTABLISH SEDIMENT CONTROLS AROUND CATCH BASINS
3) PRIOR TO FINAL APPROVAL FOR ENGINEERING, ALL STORM DRAIN CATCH BASINS MUST BE CLEANED OUT.
4) SOME UNDERGROUND STORM DRAINAGE INSTALLED, MAJORITY OF WORK AT THIS TIME BEING DONE IS ON THE BLDG ITSELF.
5) PERIMETER SWPPP CONTROLS ARE IN PLACE AND MUST BE MAINTAINED. ENSURE MAINT SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED.
12/08/2010 STORMWATER FOLLOW-UP INSP MRUSSO Approved 1) SITE IS UNDER A STORM WATER PERMIT AND MUST COMPLY WITH THE APPROVED STORM WATER PLAN UNTIL THE SITE IS 100% PAVED.
2) RE-ESTABLISH SEDIMENT CONTROLS AROUND CATCH BASINS
3) PRIOR TO FINAL APPROVAL FOR ENGINEERING, ALL STORM DRAIN CATCH BASINS MUST BE CLEANED OUT.
4) SOME UNDERGROUND STORM DRAINAGE INSTALLED, MAJORITY OF WORK AT THIS TIME BEING DONE IS ON THE BLDG ITSELF.
5) PERIMETER SWPPP CONTROLS ARE IN PLACE AND MUST BE MAINTAINED. ENSURE MAINT SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED.
08/11/2011 GRADING - TIER REV MRUSSO Approved
08/11/2011 GRADING - FINAL MRUSSO Approved
08/11/2011 LANDSCAPE INSPECTION MRUSSO Approved
08/18/2011 ZONING - FINAL MRUSSO Approved
06/24/2019 GRADING - CHECK FOR ACTIVITY RLEDONNE Approved
06/24/2019 GRADING - REBAR RLEDONNE Approved