Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Final
Type:
Grading and SWPPP
Apply Date:
06/02/2009
Applicant:
KEITH RABENNECK
Description:
GRADING FOR NEW SUBDIVISION
Contractors:
  • STRUNK EXCAVATING INC , R W

Permit Reviews

Permit Number - T09BU00796
Permit Status: Final
Permit Description: GRADING FOR NEW SUBDIVISION
Start Date Submittal Complete Date Status  
06/02/2009 GRADING 06/02/2009 COMPLETED Review Details
06/02/2009 GRADING 07/27/2009 COMPLETED Review Details
07/27/2009 RESUBMITTAL - GRADING ALL 08/25/2009 COMPLETED Review Details
08/25/2009 GRADING 08/25/2009 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T09BU00796
Permit Status: Final
Permit Description: GRADING FOR NEW SUBDIVISION
Total Outstanding Activity Conditions - 1
Date Name
06/02/2009 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T09BU00796
Permit Description: GRADING FOR NEW SUBDIVISION
Total Completed Inspections - 13
Date Description Inspector Results Comments
08/03/2009 NPPO PRE PERMIT INSPECTION ACONNOR Approved
08/03/2009 ENGINEERING PRE-CONSTRUCTION MRUSSO Approved 1) INSTALL WADDLE (SILT SOCK) ALONG EAST PERIMETER FROM ROADWAY TO THE SOUTH 240'.
2) INSTALL A STABILIZED CONSTRUCTION ENTRANCE PER YOUR SWPPP.
3) SWEEP UP TRACKING OF SOIL OFF PUBLIC ROADWAY ROUTINELY.
4) MAINTAIN AND INSPECT SEDIMENT CONTROLS PER PLAN AND DOCUMENT THE INSPECTIONS.
5) INSTALL A CONCRETE/MATERIALS WASH OUT ON SITE WHEN APPLICABLE.

CALL FOR REINSPECTION/APPROVAL OF INSTALL.
08/06/2009 STORMWATER INSTALL OF CONTROLS MRUSSO Approved SEDIMENT CONTROLS HAVE BEEN INSTALLED PER PRECON MEETING AGREEMENT AND THE SWPPP.
1) ENSURE A CONCRETE/MATERIALS WASH OUT IS INSTALLED WHEN APPLICABLE.
2) CONTINUE TO SWEEP UP TRACKING OFF OF PUBLIC ROADWAY.
3) MAINTAIN STORM WATER CONTROLS THROUGHOUT THE DURATION OF CONSTRUCTION.

ALL FURTHER STORM WATER INSPECTION WILL BE ADDRESSED UNDER #09154 STORM WATER FOLLOW UP INSPECTIONS.
12/04/2009 STORMWATER FOLLOW-UP INSP MRUSSO Approved NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME


ENG OF RECORD PROVIDED A STATEMENT CHANGING THE VERTICAL CURB AND FOOTER SHOWN ON APPROVED PLAN ALONG WEST PERIMETER OF SITE TO THE STANDARD VERTICAL CURB DUE TO THE FACT THAT THE DIFFERENCE IN ELEVATION BETWEEN THE ROAD AND NATURAL GROUND IS NOT AS GREAT AS FIRST THOUGHT. SEE COPY OF STATEMENT IN FILE
12/04/2009 GRADING - INTERMEDIATE MRUSSO Approved ENG OF RECORD PROVIDED A STATEMENT CHANGING THE VERTICAL CURB AND FOOTER SHOWN ON APPROVED PLAN ALONG WEST PERIMETER OF SITE TO THE STANDARD VERTICAL CURB DUE TO THE FACT THAT THE DIFFERENCE IN ELEVATION BETWEEN THE ROAD AND NATURAL GROUND IS NOT AS GREAT AS FIRST THOUGHT. SEE COPY OF STATEMENT IN FILE
12/04/2009 GRADING - TIER REV MRUSSO Approved ENG OF RECORD PROVIDED A STATEMENT CHANGING THE VERTICAL CURB AND FOOTER SHOWN ON APPROVED PLAN ALONG WEST PERIMETER OF SITE TO THE STANDARD VERTICAL CURB DUE TO THE FACT THAT THE DIFFERENCE IN ELEVATION BETWEEN THE ROAD AND NATURAL GROUND IS NOT AS GREAT AS FIRST THOUGHT. SEE COPY OF STATEMENT IN FILE.
01/08/2010 GRADING - FINAL MRUSSO Approved SITE HAS BEEN CONSTRUCTED PER THE APPROVED GRADING PLAN.
01/08/2010 STORMWATER FINAL INSPECTION MRUSSO Approved SITE HAS BEEN STABILIZED
01/08/2010 GRADING - FINAL MRUSSO Approved
01/08/2010 GRADING - CHECK FOR ACTIVITY MRUSSO Approved
01/14/2010 LANDSCAPE INSPECTION ACONNOR Approved
01/19/2010 PERMIT FINALED KMEDINA Approved
06/17/2019 GRADING - REBAR RLEDONNE Approved

Documents

File Name Document Type  
001_PAGE 1 OF 2.TIF GRADING PLANS VIEW
002_PAGE 2 OF 2.TIF GRADING PLANS VIEW
None DOCUMENTS VIEW
CERTIFICATION LETTER 2009_12_02.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW