Permit: T08CM03271
Permit Details
Apply Date:
10/06/2008
Applicant:
N/A
Description:
TI: RETAIL
Contractors:
- DAMITIO CONSTRUCTION INC ,
Permit Reviews
Permit Number - T08CM03271
Permit Status: C of o
Permit Description: TI: RETAIL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
10/06/2008 | COMMERCIAL TI | 10/10/2008 | COMPLETED |
10/10/2008 | RESUBMITTAL | 10/10/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM03271
Permit Status: C of o
Permit Description: TI: RETAIL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/06/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM03271
Permit Description: TI: RETAIL
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/08/2008 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* ALL RECTANGULAR DUCT WORK IN ATTIC MUST BE LINED WITH MIN. R4.2 LINER (1") PLANS REQUIRE INSULATED CONDENSATE PIPING OK TO SHEETROCK HARD LIDS |
12/08/2008 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1. WALLS IN BOTH BATHROOMS OK 2. WEST WALL OK 3. NORTH WALL OK |
12/09/2008 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
12/11/2008 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO TAPE THROUGHOUT |
12/11/2008 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
12/22/2008 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
12/29/2008 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
12/29/2008 | PLUMBING - PROGRESS | RRICH | Approved | IVRS - Inspection :* |
12/29/2008 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
12/29/2008 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
12/29/2008 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
12/29/2008 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
12/31/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* 1) PROVIDE APPROVED SUPPORT FOR EXPANSION TANK 2) COMPLETE LIST FROM 12/29/08 |
12/31/2008 | ELECTRIC - ABOVE CEILING | RMORENO | Approved | IVRS - Inspection :* 1) POWER POLES WILL BE DONE LATER ON TENANT PERMIT, EM LIGHTING ON SAME PERMIT AS TENANT |
12/31/2008 | MECHANICAL - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
12/31/2008 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
01/02/2009 | NPPO - FINAL | ACONNOR | Approved | N/A |
01/02/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
01/02/2009 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
01/02/2009 | ENGINEERING - FINAL | JBRUCKME | Approved | |
01/06/2009 | FIRE - FINAL | LTHOMAS | Approved | |
01/07/2009 | SIGN - FINAL | JYBARRA | Approved | |
01/14/2009 | BUILDING - FINAL | JBURGE | Approved |