Permit: T08CM02517
Permit Details
Apply Date:
07/21/2008
Applicant:
N/A
Description:
NEW OFFICE BUILDING
Architects:
- MORROW, KEVIN THOMAS
Contractors:
- BARKER MORRISSEY CONTRACTING INC **C
Permit Reviews
Permit Number - T08CM02517
Permit Status: C of o
Permit Description: NEW OFFICE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/28/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 01/28/2009 | COMPLETED |
| 03/09/2009 | 3RD PARTY REVIEW-REVISION/OTHER | 03/19/2009 | COMPLETED |
| 07/21/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 07/21/2008 | COMPLETED |
| 07/21/2008 | 3RD PARTY REVIEW-COMMERCIAL | 09/24/2008 | COMPLETED |
| 09/24/2008 | POST 3RD PARTY REVIEW | 11/20/2008 | COMPLETED |
| 11/20/2008 | POST 3RD PARTY REVIEW | 12/03/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM02517
Permit Status: C of o
Permit Description: NEW OFFICE BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 07/21/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM02517
Permit Description: NEW OFFICE BUILDING
Total Completed Inspections - 49
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/11/2008 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* |
| 12/11/2008 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
| 12/17/2008 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* PETITION OF APPEAL ON SITE #08-12-08 FOR USE OF IPC IN PLACE OF UPC PER PLAN. WITH REVISION THIS WILL NEED TO BE ON REVISED PLAN. FROM INITIAL ON P1.1 THRU TO C/O AND (3) FLOOR SINKS FOR CWV SYSTEM PER 2006 IPC WITH TRAP PRIMERS |
| 12/17/2008 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* |
| 12/19/2008 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* 1. OK 4/0 FOR CONNECTION TO LIGHTNING PROTECTION SYSTEM 2. OK U.G FOR FLOOR BOXES 3. OK GEC FOR XFMR CONNECTED TO 4/0 UFER |
| 12/19/2008 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* STAIRWELL STEM WALL @ 5.5/A.0 TO 6.5/A.0 SPECIAL INSPECTED |
| 12/19/2008 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* |
| 12/22/2008 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* FROM LINE C NORTH PRE-SLAB OK 4" RWL WATER TEST TO 2' AFF FOR SOUTHEAST CORNER |
| 12/22/2008 | PLUMBING - ROOF DRAINS | RRICH | Approved | IVRS - Inspection :* |
| 12/31/2008 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* 1) CONCRETE PIER CAP FOOTING AT GRID E.0/1.0-SPECIAL INSPECTED |
| 12/31/2008 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* 1) REINFORCING BAR FOR PRE-SLAB A GRID LOCATIONS FROM 1.0/A.0 TO 8.0/A.0 SOUTH TO 1.0/C.0 TO 8.0/C.0 OK-SPECIAL INSPECTED |
| 01/22/2009 | RIGHT OF WAY - FINAL | MCASTRO | Approved | |
| 03/02/2009 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* FROM METER THRU TO CAPS ON ROOF PER DELTA 4 BLUE PAGES REVISION WHICH WILL NEED C.O.T APPROVAL |
| 03/18/2009 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 04/06/2009 | STUCCO MESH | GDABBS | Approved | IVRS - Inspection :* |
| 04/06/2009 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 04/16/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. JIROUDEK |
| 04/20/2009 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* PLEASE CALL IN 03005, 03035, 03040 FOR APPROVAL |
| 04/20/2009 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* |
| 04/20/2009 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 04/21/2009 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
| 04/27/2009 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* GRID COMPLETE |
| 05/05/2009 | SIGN - FINAL | JYBARRA | Approved | |
| 05/05/2009 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
| 05/05/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
| 05/05/2009 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
| 05/05/2009 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 05/05/2009 | U VALUE FOR WINDOW | GDABBS | Approved | IVRS - Inspection :* |
| 05/05/2009 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 05/05/2009 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
| 05/06/2009 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 05/07/2009 | FUEL TANK FINAL 791-4502 | CFUNKE | Approved | Approved. Refer to T08BU01991 |
| 05/08/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* COPPER DRAIN LINES PENETRATING CABINET OF FAN COILS MUST BE PROTECTED AT KNOCKOUT. NEED AIR BALANCE REPORT NEED DUCT SMOKE DETECTOR TEST |
| 05/11/2009 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
| 05/11/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 05/11/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 05/13/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 05/14/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 05/15/2009 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1) PLUMBING FINAL OK |
| 05/18/2009 | FIRE - FINAL | LTHOMAS | Approved | PER INSP COPY |
| 05/19/2009 | NPPO - FINAL | ACONNOR | Approved | |
| 05/19/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 10/27/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 10/27/2009 | ELECTRIC - TEMP POWER FOR TEST | RJIROUDE | Approved | IVRS - Inspection :* |
| 10/27/2009 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 10/27/2009 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
| 10/27/2009 | ENGINEERING - FINAL | JFEMLING | Approved | All items complete, approved. |
| 10/30/2009 | PERMIT FINALED | JWEATHER | Approved | |
| 10/30/2009 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |