Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T08CM01565
Permit Details
Apply Date:
05/14/2008
Applicant:
N/A
Description:
NEW APARTMENT BUILDING #5
Architects:
- MCQUILLEN, THOMAS
Contractors:
- TOFEL CONSTRUCTION
Permit Reviews
Permit Number - T08CM01565
Permit Status: C of o
Permit Description: NEW APARTMENT BUILDING #5
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/04/2009 | RESUBMITTAL | 09/28/2009 | COMPLETED |
05/14/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 05/14/2008 | COMPLETED |
05/14/2008 | 3RD PARTY REVIEW-COMMERCIAL | 09/22/2008 | COMPLETED |
09/22/2008 | POST 3RD PARTY REVIEW | 02/04/2009 | COMPLETED |
10/06/2009 | REVISION - - 1ST | 11/04/2009 | COMPLETED |
11/04/2009 | REVISION - - 1ST | 11/10/2009 | COMPLETED |
11/10/2009 | REVISION - - 1ST | 11/19/2009 | COMPLETED |
11/19/2009 | REVISION - - 3RD | 11/23/2009 | ACTIVE |
11/19/2009 | REVISION - - 2ND | 11/19/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM01565
Permit Status: C of o
Permit Description: NEW APARTMENT BUILDING #5
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/14/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM01565
Permit Description: NEW APARTMENT BUILDING #5
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/19/2009 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1) PVC SCHEDULE 40 UNDERGROUND DWV OK TO COVER |
10/23/2009 | ELECTRIC - UNDERGROUND | RMORENO | Approved | IVRS - Inspection :* ROM EDSD BUILDING TO WEST CENTER OF BUILDING OK TRENCH 2*4", 1.3, 1 1 1/2 ALL OK |
11/04/2009 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) UFER #2 OK 3 PHASE HOUSE PANLE 2HA1 OK 200 A, UFER #2 PANEL 2A 800 A |
11/05/2009 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* 1) CONDENSATE AND T & P RELIEF DRAIN INSTALLED PER PLAN 2) OK TO CONCRETE |
11/05/2009 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* 1) BLDG SLAB OK TO POUR 2) COMPLIANT WESTERN TECH SPECIAL INSPECTION |
11/18/2009 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | 1) FOOTING/MC1 AS PER DETAILS #113 & 114 PAGE S3.0-OK TO POUR FOOTING |
12/02/2009 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | MASONRY PRE-GROUT PARTIAL 10 COLUMNS TOPPED OUT @9' - OK TO GROUT PROGRESS AREAS. |
12/18/2009 | BUILDING - PROGRESS | JBURGE | Approved | IVRS - Inspection :* 1) 2ND FLOOR SUB FLOOR OK TO FRAME |
03/05/2010 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
03/09/2010 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* 1) OK TO STUCCO MESH |
03/18/2010 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1) PEX OK 2) PVC OK 3) FLANGES OK |
05/12/2010 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO TAPE THROUGHOUT |
06/16/2010 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
07/02/2010 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO SET CEILING TILES |
07/07/2010 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
07/28/2010 | ELECTRIC - FINAL | RMORENO | Approved | IVRS - Inspection :* |
08/05/2010 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* |
08/05/2010 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
08/05/2010 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
08/05/2010 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* |
08/06/2010 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
08/06/2010 | MECHANICAL - PROGRESS | MRAMBER | Approved | IVRS - Inspection :* |
08/06/2010 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
08/06/2010 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
08/09/2010 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
08/09/2010 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
08/09/2010 | FIRE - FINAL | LTHOMAS | Approved | |
08/09/2010 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
08/09/2010 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* |
08/11/2010 | ELECTRIC - UFER | RMORENO | Approved | |
08/11/2010 | OUTDOOR LIGHTING FINAL | RMORENO | Approved | |
08/11/2010 | ELECTRIC - OUTDOOR LIGHTING | RMORENO | Approved | |
08/11/2010 | ELECTRIC - PROGRESS | RMORENO | Approved | |
08/11/2010 | ELECTRIC - RECONNECT | RMORENO | Approved | |
08/11/2010 | ELECTRIC - CONSTRUCTION POWER | RMORENO | Approved | |
08/11/2010 | ROOF NAILING | JBURGE | Approved | |
08/11/2010 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |