Permit: T08CM01522
Permit Details
Apply Date:
05/13/2008
Applicant:
N/A
Description:
TI: OFFICE
Contractors:
- S K BUILDERS INC
Permit Reviews
Permit Number - T08CM01522
Permit Status: C of o
Permit Description: TI: OFFICE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/13/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 05/14/2008 | COMPLETED |
05/14/2008 | 3RD PARTY REVIEW-COMMERCIAL TI | 06/13/2008 | COMPLETED |
06/13/2008 | POST 3RD PARTY REVIEW | 07/15/2008 | COMPLETED |
07/15/2008 | REVISION - - 1ST | 07/16/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM01522
Permit Status: C of o
Permit Description: TI: OFFICE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/13/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM01522
Permit Description: TI: OFFICE
Total Completed Inspections - 25
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/18/2008 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* |
06/18/2008 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* |
06/19/2008 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* PLUMBING INFILLS AND BEARING WALL FOOTINGS PLUS COLUMN SPREAD FOOTINGS |
06/19/2008 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* |
07/16/2008 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* |
07/16/2008 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* OK FOR SHEETROCK WILL CHECK T-BAR CEILINGS ON FINAL |
07/16/2008 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
07/17/2008 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
07/17/2008 | ELECTRIC - INTERMEDIATE | RJIROUDE | Approved | IVRS - Inspection :* |
07/17/2008 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
07/24/2008 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
08/28/2008 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* CLOSET FLANGES OK |
08/28/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
08/28/2008 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
08/28/2008 | FIRE - FINAL | LTHOMAS | Approved | |
09/18/2008 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
09/18/2008 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
09/18/2008 | NPPO - FINAL | ACONNOR | Approved | |
09/18/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
09/18/2008 | ENGINEERING - FINAL | NKALAHAR | Approved | SITE WORK ALREADY COMPLETE |
09/19/2008 | RIGHT OF WAY - FINAL | MCASTRO | Approved | PER EMAIL |
09/22/2008 | PLUMBING - FINAL | GDABBS | Approved | |
09/22/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
09/22/2008 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
09/22/2008 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |