Permit: T08CM00660
Permit Details
Apply Date:
02/27/2008
Applicant:
N/A
Description:
TI:ADA REQUIREMENTS
Contractors:
- TWO J S PLUMBING AND CONSTRUCTION
Permit Reviews
Permit Number - T08CM00660
Permit Status: Final
Permit Description: TI:ADA REQUIREMENTS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/27/2008 | PLANS OK TO SUBMIT - COMM | 02/27/2008 | COMPLETED |
| 02/27/2008 | COMMERCIAL TI | 05/06/2008 | COMPLETED |
| 05/06/2008 | RESUBMITTAL | 05/23/2008 | COMPLETED |
| 05/23/2008 | RESUBMITTAL | 06/02/2008 | COMPLETED |
| 06/02/2008 | RESUBMITTAL | 06/11/2008 | COMPLETED |
| 06/11/2008 | RESUBMITTAL | 06/12/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00660
Permit Status: Final
Permit Description: TI:ADA REQUIREMENTS
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 02/27/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM00660
Permit Description: TI:ADA REQUIREMENTS
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/30/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* ROOMS #144, 145, 146, 129, 130, 108, 106 ROUGH SOIL AND PRE-SLAB OK |
| 07/07/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* CALL FOR FINAL WHEN READY |
| 07/07/2008 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 07/28/2008 | FRAMING | MHENSON | Approved | IVRS - Inspection :* |
| 08/06/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 08/06/2008 | BUILDING - PROGRESS | MHENSON | Approved | IVRS - Inspection :* |
| 08/08/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 08/08/2008 | PLUMBING - PROGRESS | RLEDONNE | Approved | IVRS - Inspection :* |
| 08/19/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 08/19/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 08/21/2008 | FIRE - ALARM FINAL | CSCHULTZ | Approved | |
| 08/21/2008 | FIRE - FINAL | CSCHULTZ | Approved | |
| 08/22/2008 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* |
| 08/25/2008 | PERMIT FINALED | BFLORES | Approved |