Permit: T08CM00224
Permit Details
Apply Date:
01/22/2008
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW:INDUSTRIAL SHELL BUILDING
Architects:
- MORROW, KEVIN THOMAS
Contractors:
- CHESTNUT CONSTRUCTION CORPORATIO
Permit Reviews
Permit Number - T08CM00224
Permit Status: Final
Permit Description: NEW:INDUSTRIAL SHELL BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/22/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 01/22/2008 | COMPLETED |
01/22/2008 | 3RD PARTY REVIEW-COMMERCIAL | 03/25/2008 | COMPLETED |
03/25/2008 | POST 3RD PARTY REVIEW | 04/11/2008 | COMPLETED |
04/21/2008 | RESUBMITTAL | 05/06/2008 | COMPLETED |
05/06/2008 | RESUBMITTAL | 05/14/2008 | COMPLETED |
09/17/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 11/05/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00224
Permit Status: Final
Permit Description: NEW:INDUSTRIAL SHELL BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/22/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T08CM00224
Permit Description: NEW:INDUSTRIAL SHELL BUILDING
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/09/2008 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* CLEANOUT UNDER SLAB TEST OK |
09/19/2008 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
11/05/2008 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* BALANCE OF BUILDING CLOSURE POUR |
11/14/2008 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
11/20/2008 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* COMPLETE -- OK TO COVER |
12/10/2008 | STEM WALL/RETAINING WALL | GDABBS | Approved | NORTHWEST STORE FRONT RETAINING WALL |
12/15/2008 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
12/17/2008 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* OK SOFFITS AT ENTRIES |
12/17/2008 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* EAST SIDE SITE WALL 0' TO 5' OK |
12/18/2008 | PLUMBING - BACK WATER VALVE | RLEDONNE | Approved | IVRS - Inspection :* PROVIDE VENT FOR SEWER |
12/18/2008 | FRAMING | GDABBS | Approved | IVRS - Inspection :* STOREFRONT SHEATHING & FRAMING @ WEST END OF BLDG. |
12/22/2008 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* 2 1/2" PVC TRACER WIRE BEDDING OK UP 5' FROM BUILDING BACKFLOW IS INSTALLED TEST OK |
12/23/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* CANCELED |
12/30/2008 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* 1) THIRD DOCK RAMP WALL REINFORCEMENT FROM WEST 2) 1ST AND 3RD ENTRY LID MESH-OK |
12/30/2008 | STUCCO MESH | GDABBS | Approved | IVRS - Inspection :* |
01/07/2009 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
02/13/2009 | SIGN - FINAL | LHANLY | Approved | IVRS - Inspection :* |
02/18/2009 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* |
02/18/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR "HOUSE PANEL" PER D. SANTACRUZ |
02/24/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
02/24/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
02/24/2009 | FIRE - FINAL | LTHOMAS | Approved | |
03/02/2009 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
03/02/2009 | PLUMBING - ROOF DRAINS | RLEDONNE | Approved | IVRS - Inspection :* |
03/04/2009 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
03/04/2009 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
03/04/2009 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
03/16/2009 | NPPO - FINAL | ACONNOR | Approved | |
03/16/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
04/06/2009 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* |
04/27/2009 | ENGINEERING - FINAL | MAVERY | Approved | NEED LETTER FROM ENGINEER ADDRESSING PONDING AT TRASH ENCLOSURE. WILL HOLD T.I. ON SUITE #180 (T09CM00355) |