Permit: T07CM03503
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
3565 E SPEEDWAY BL #171
Address NEW:
3565 E SPEEDWAY BL #171
Apply Date:
08/24/2007
Applicant:
N/A
Description:
TI:MARKET
Architects:
- MIREK EDWARD
Contractors:
- INLINE CONSTRUCTION INC
Permit Reviews
Permit Number - T07CM03503
Permit Status: C of o
Permit Description: TI:MARKET
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/24/2007 | OTHER | 08/24/2007 | COMPLETED |
| 08/28/2007 | RESUBMITTAL | 10/23/2007 | COMPLETED |
| 10/23/2007 | REVISION - - 1ST | 10/24/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM03503
Permit Status: C of o
Permit Description: TI:MARKET
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/24/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM03503
Permit Description: TI:MARKET
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/03/2007 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 10/12/2007 | FRAMING | JBURGE | Approved | IVRS - Inspection :* OK TO SHEETROCK |
| 10/12/2007 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 10/12/2007 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 10/17/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES BE SURE EXISTING AC HAS FRESH AIR INTAKE & CONDENSATE TO AN APPROVED LOCATION |
| 10/17/2007 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO TAPE THROUGHOUT |
| 10/25/2007 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
| 10/25/2007 | NPPO - FINAL | ACONNOR | Approved | N/A |
| 10/25/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | N/A |
| 10/25/2007 | SIGN - FINAL | JYBARRA | Approved | |
| 10/26/2007 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | IVRS - Inspection :* |
| 10/26/2007 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* |
| 10/26/2007 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 10/29/2007 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* PLUMBING FINAL OK OK FOR C OF O |
| 10/29/2007 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | |
| 10/29/2007 | FIRE - FINAL | CSCHULTZ | Approved | |
| 10/29/2007 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1. REMOVE 4" TEST PLUG AND INSTALL COUNTER SUNK TAPPED PLUG W/CP COVER 2. PAINT VENT TERMINAL 3. ALL HOT WATER AND RETURN PIPING TO BE INSULATED 4. WILL REQUIRE APPROVED HEALTH DEPT. PLAN |
| 10/30/2007 | PLUMBING - PROGRESS | RMYERS | Approved | IVRS - Inspection :* |
| 10/31/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR FINAL AIR BALANCE OK |
| 10/31/2007 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 11/01/2007 | BUILDING - FINAL | JBURGE | Approved |