Permit: T07CM03277
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
630 N ALVERNON WY #200
Address NEW:
630 N ALVERNON WY #200
Apply Date:
08/06/2007
Applicant:
N/A
Description:
TI:OFFICE
Architects:
- LANCE, GEORGE GERARD
Contractors:
- EPSTEIN FENTON L L C ,
Permit Reviews
Permit Number - T07CM03277
Permit Status: C of o
Permit Description: TI:OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/06/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 08/06/2007 | COMPLETED |
| 08/06/2007 | 3RD PARTY REVIEW-COMMERCIAL TI | 08/30/2007 | COMPLETED |
| 08/30/2007 | POST 3RD PARTY REVIEW | 09/18/2007 | COMPLETED |
| 10/25/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 11/14/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM03277
Permit Status: C of o
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/06/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM03277
Permit Description: TI:OFFICE
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/04/2007 | FRAMING | JBURGE | Approved | IVRS - Inspection :* OK TO SHEETROCK ONE SIDE |
| 10/12/2007 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO TAPE |
| 10/18/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* OK FOR SHEETROCK SUSPENDED ROUGH DUCT OK TO PROCEED |
| 11/14/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* WHERE IS THE EQUIPMENT SCHEDULE ON PLANS FOR THE NEW MINI-SPLIT SYSTEM INSTALLED? REVISE PLANS AS NECESSARY. OK FOR CEILING TILES NEED TO CHANGE EXISTING PNEUMATIC CONTROLS AS PER PLANS. |
| 12/03/2007 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* PENETRATIONS PROPERLY FIRE CAULKED - T-GRID SYSTEM IN PLACE |
| 12/04/2007 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 12/04/2007 | SIGN - FINAL | JYBARRA | Approved | |
| 12/04/2007 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
| 12/04/2007 | NPPO - FINAL | ACONNOR | Approved | |
| 12/04/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 12/06/2007 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | |
| 12/06/2007 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | |
| 12/06/2007 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 12/06/2007 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 12/06/2007 | FIRE - FINAL | LTHOMAS | Approved | |
| 12/12/2007 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* RECEIVED ALL PAPER WORK |
| 12/12/2007 | ELECTRIC - RECONNECT | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/12/2007 | ELECTRIC - CONSTRUCTION POWER | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/12/2007 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/12/2007 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/17/2007 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* PENDING AIR BALANCE REPORT |
| 12/18/2007 | PERMIT FINALED | JMILITEL | Approved | |
| 12/18/2007 | MECHANICAL - FINAL | JMILITEL | Approved |