Permit Status: C of o
Permit Description: TI:HOSPITAL PHARMACY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/23/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 01/25/2008 | COMPLETED |
04/17/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 04/17/2007 | COMPLETED |
04/17/2007 | 3RD PARTY REVIEW-COMMERCIAL TI | 05/03/2007 | COMPLETED |
05/03/2007 | POST 3RD PARTY REVIEW | 08/10/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM01595
Permit Status: C of o
Permit Description: TI:HOSPITAL PHARMACY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
04/17/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T07CM01595
Permit Description: TI:HOSPITAL PHARMACY
Total Completed Inspections - 24
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/13/2007 | FRAMING | JBURGE | Approved | IVRS - Inspection :* PHASE 1 - OK TO SHEETROCK PENDING ELECTRIC INTERMEDIATE |
09/21/2007 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* OK WALL COVER PANELS "3BE" "BP2" AREA OK UNDERGROUND RACEWAY TO ORDER ENTRY DESK |
09/21/2007 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
10/17/2007 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* PHASE 1 OK |
10/17/2007 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | IVRS - Inspection :* |
10/18/2007 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
10/18/2007 | NPPO - FINAL | ACONNOR | Approved | |
10/18/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
10/18/2007 | ENGINEERING - FINAL | MRUSSO | Approved | |
10/18/2007 | SIGN - FINAL | JYBARRA | Approved | |
10/18/2007 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection :* OK TO COVER OVERHEAD |
10/19/2007 | MECHANICAL - HOOD SYSTEMS | MRAMBER | Approved | IVRS - Inspection :* |
10/19/2007 | MECHANICAL - HOODS | MRAMBER | Approved | IVRS - Inspection :* |
10/25/2007 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | IVRS - Inspection :* OK CEILING TILES IN PHASE 1 OF PHARMACY AREA CKTS (2) STILL LEFT TO BE ALTERED WILL BE LOOKED AT WHEN COMPLETED. |
10/25/2007 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* PROVIDE SUPPORT ON FLEX RUNS INSULATE RE-HEAT PIPING @ V.A.V'S |
10/30/2007 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* RESTROOM 002Q & SINK P-3 IN PHARMACY AREA OK FOR FINAL |
10/30/2007 | FIRE SPKLR - FINAL | LTHOMAS | Approved | Phase 1 |
10/30/2007 | FIRE - FINAL | LTHOMAS | Approved | Phase 1 |
10/30/2007 | ELECTRIC - CONSTRUCTION POWER | CCLEMENS | Approved | IVRS - Inspection :* |
10/31/2007 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* PHASE 1 OK SEE BLDG. INSPECTOR FOR TEMP |
11/01/2007 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* PHASE 1 OK TEMP C OF O |
11/05/2007 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* OK PHARMACY AREA WHEN EMERGENCY LIGHTING TEST IS COMPLETE, CALL THIS FINAL INSPECTION IN AGAIN AND PROVIDE WRITTEN RESULTS OF TEST. |
11/06/2007 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* MECH ROOM FLOOR SINK TIE IN IN MECH ROOM 0402B |
02/29/2008 | PERMIT FINALED | LJACKSON | Approved |