Permit: T07BU02263
Permit Details
Apply Date:
10/26/2007
Applicant:
N/A
Description:
GRADING: CUT 25CY FILL 550CY
Contractors:
- MAGNUM PAVING INC
Permit Reviews
Permit Number - T07BU02263
Permit Status: Final
Permit Description: GRADING: CUT 25CY FILL 550CY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/21/2008 | REVISION - GRADING | 02/21/2008 | COMPLETED |
02/21/2008 | REVISION - GRADING | 06/25/2008 | COMPLETED |
06/25/2008 | REVISION - GRADING | 06/25/2008 | COMPLETED |
06/25/2008 | REVISION - GRADING | 07/08/2008 | COMPLETED |
10/09/2008 | REVISION - GRADING | 11/05/2008 | COMPLETED |
10/26/2007 | PLANS OK TO SUBMIT - GRADING | 10/26/2007 | COMPLETED |
10/26/2007 | GRADING | 12/18/2007 | COMPLETED |
12/18/2007 | GRADING | 01/18/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07BU02263
Permit Status: Final
Permit Description: GRADING: CUT 25CY FILL 550CY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/26/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07BU02263
Permit Description: GRADING: CUT 25CY FILL 550CY
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/23/2008 | ENGINEERING PRE-CONSTRUCTION | MAVERY | Approved | Completed pre-con with Gale with Gadsden and Ben with Magnun. |
09/22/2008 | GRADING - INTERMEDIATE | MAVERY | Approved | Met on site with super to look at stormwater piping. Contractor backfilled all piping. Contractor will need to provide letter from engineer per 11-01.16.2 (built to spec). |
09/04/2009 | GRADING - CHECK FOR ACTIVITY | JFEMLING | Approved | |
09/04/2009 | STORMWATER FOLLOW-UP INSP | JFEMLING | Approved | Approved |
12/23/2010 | GRADING - FINAL | JFEMLING | Approved | Complete items 1,2,3,5 from the previous punch list, and install bike parking per the approved plan, remove all construction materials and debris or separate from the public, install pavers at the rear of building per plan, provide as-built drawings. |
12/23/2010 | LANDSCAPE INSPECTION | JFEMLING | Approved | Provide an approved set of plans for inspection |