Permit: T06CM05984
Permit Details
Apply Date:
11/20/2006
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW BLDG:AIRPORT RUN
Architects:
- MORROW, KEVIN THOMAS
Contractors:
- J R TUTTLE CO
Permit Reviews
Permit Number - T06CM05984
Permit Status: C of o
Permit Description: NEW BLDG:AIRPORT RUN
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/25/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 01/25/2007 | COMPLETED |
| 01/25/2007 | 3RD PARTY REVIEW-COMMERCIAL | 03/22/2007 | COMPLETED |
| 02/13/2007 | RESUBMITTAL - SITE ALL | 03/30/2007 | COMPLETED |
| 02/14/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 02/15/2008 | COMPLETED |
| 03/22/2007 | POST 3RD PARTY REVIEW | 07/17/2007 | COMPLETED |
| 05/04/2007 | RESUBMITTAL - SITE ALL | 07/14/2007 | COMPLETED |
| 05/17/2007 | OTHER | 05/17/2007 | COMPLETED |
| 05/17/2007 | RESUBMITTAL | 07/27/2007 | COMPLETED |
| 11/05/2007 | POST 3RD PARTY REVIEW | 11/14/2007 | COMPLETED |
| 11/14/2007 | RESUBMITTAL | 11/15/2007 | COMPLETED |
| 11/20/2006 | PLANS OK TO SUBMIT - SITE | 11/21/2006 | COMPLETED |
| 11/21/2006 | SITE | 01/03/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM05984
Permit Status: C of o
Permit Description: NEW BLDG:AIRPORT RUN
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/20/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM05984
Permit Description: NEW BLDG:AIRPORT RUN
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/28/2007 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* STEMS LINE G & A LINE D 3 & 4 ALSO, PERIMETERS AS SHOWN IN COMPLIANCE TO SP. INSP. |
| 10/16/2007 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* OK UFER SUBJECT TO LISTING INFO. FOR CLAMP USED |
| 10/29/2007 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | IVRS - Inspection :* |
| 11/26/2007 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 11/26/2007 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
| 11/27/2007 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/29/2007 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/06/2007 | BUILDING PRE-SLAB | MHENSON | Approved | IVRS - Inspection :* OK TO POUR RESTROOM |
| 12/13/2007 | SITE - SEWER | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/13/2007 | PLUMBING - SEWER HCS CONNECT | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/17/2007 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 12/18/2007 | FRAMING | MHENSON | Approved | IVRS - Inspection :* ALL EXCEPT BATHROOMS NEEDS BACKING ADA |
| 12/27/2007 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* 1) PROVIDE E.F. THROUGH ROOF PRIOR TO FINAL |
| 12/27/2007 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* 1) USE APPROVED MEANS OF SUPPORT FOR VDV CABELING 2) VERIFY FITTINGS FOR EMBEDDING IN CONCRETE 3) SUPPORT CONDUITS 10' + 3' 4) OK EXCEPT AS NOTE-WALLS |
| 01/14/2008 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
| 01/23/2008 | SHEET ROCK NAILING | MHENSON | Approved | IVRS - Inspection :* |
| 02/14/2008 | BUILDING ABOVE CEILING | MHENSON | Approved | IVRS - Inspection :* |
| 02/14/2008 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection :* |
| 02/14/2008 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 02/15/2008 | U VALUE FOR WINDOW | MHENSON | Approved | IVRS - Inspection :* |
| 02/15/2008 | FIRE - FINAL | LTHOMAS | Approved | |
| 02/15/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
| 02/19/2008 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* CLOSET FLANGES OK |
| 02/19/2008 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 02/19/2008 | SIGN - FINAL | JYBARRA | Approved | |
| 03/21/2008 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 03/24/2008 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 03/27/2008 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 04/04/2008 | NPPO - FINAL | ACONNOR | Approved | |
| 04/04/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 04/09/2008 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | |
| 04/09/2008 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 04/09/2008 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 05/02/2008 | BUILDING - FINAL | MHENSON | Approved | IVRS - Inspection :* |
| 05/02/2008 | STEM WALL/RETAINING WALL | MHENSON | Approved | IVRS - Inspection :* |
| 05/02/2008 | ENGINEERING - FINAL | MAVERY | Approved | Contractor provided asbuilts for site. Approved by Sunrise Engineering. |
| 05/05/2008 | PERMIT FINALED | BFLORES | Approved |